Failed: Electrical - Temporary Service |
Panel Needs To. Be Cleaned Out And Holes Plugged |
Matt Forsyth |
10/20/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
10/21/2020 |
Release to power company |
|
Matt Forsyth |
10/21/2020 |
Passed: Building - Footer |
|
Matt Forsyth |
10/22/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
10/22/2020 |
Passed: Building - Footer |
|
Matt Forsyth |
10/22/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
10/22/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
10/30/2020 |
Passed: Building - Monolithic Slab |
House And Porch Only |
Matt Forsyth |
11/4/2020 |
Passed: Building - Slab |
House And Porches Only |
Matt Forsyth |
11/4/2020 |
Passed: Building - Monolithic Slab |
Carport |
Matt Forsyth |
11/6/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
11/6/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
11/17/2020 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
11/17/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
12/3/2020 |
Passed: Building - Strapping |
|
Matt Forsyth |
12/3/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
12/3/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
12/3/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
12/3/2020 |
Passed: Building - Insulation |
Walls And Vaulted Ceilings Only |
Matt Forsyth |
12/21/2020 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
3/31/2021 |
Release to power company |
|
Laurie Hodson |
4/5/2021 |
Septic Release Inspection |
|
Health Dept |
4/5/2021 |
Passed: Building - Final |
|
Matt Forsyth |
4/22/2021 |