Inspection |
Notes |
Performed By |
Date |
Fire-Plan Review |
Recommend Approval Of The Building With The Conditions In The Attached Letter Dated 8.11.2020 |
Tad Cervantes |
8/11/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
9/10/2020 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
9/23/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
9/23/2020 |
Passed: Building - Framing |
|
Troy Crews |
1/5/2021 |
Passed: Building - Insulation |
Front Office Area |
Troy Crews |
1/5/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
1/5/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
1/5/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/5/2021 |
Passed: Electrical - 2nd Rough-In |
Office Areas |
Troy Crews |
2/19/2021 |
Passed: Mechanical - Rough In |
Bottom Floor |
Troy Crews |
3/4/2021 |
Passed: Electrical - Permanent Power |
Release Pending Septic Final |
Troy Crews |
3/16/2021 |
Release to power company |
|
Melissa Garber |
4/9/2021 |
Septic Release Inspection |
|
Health Dept |
4/9/2021 |
Cancelled: Electrical - Permanent Power |
|
Troy Crews |
8/23/2021 |
Failed: Building - Final |
Gate Locked No One Onsite I Have Set Up For Zoning Final Thursday May Want To Reschedule For Then |
Troy Crews |
8/24/2021 |
Failed: Engineering - Zoning Final |
Site Was Gated And Locked. Could Not Perform Complete Inspection; However, It Is Apparent That The Site Was Not Constructed As Approved. Asphalt Milling Is Not An Approved Wear Surface. Milling Must Be Removed And Replaced With Type Ii Asphaltic Concrete Per Ldrs And Approved Site Plan. Additional Comments May Follow Once A Complete Site Inspection Can Be Performed. |
Brandon Stubbs |
8/26/2021 |
Failed: Building - Final |
Need Two Handrails On All Stairs, Need Exit Light At Front Main Door, Also Two Upstairs For Exit To Stairs, Need Fire Extinguishers One At Front Door , One At Door To Garage. All Plugs Within 6 Ft. Of Sinks Need G.f.c.i. Protection, Need To Complete Storage Room In Garage, Need To Close Bottom Of Stairs In Garage For Draftstop. |
Troy Crews |
8/26/2021 |
Failed: Fire - Fire Final |
Missing Light Weight Truss Marking, Emergency Lighting/exit Signs, Fire Extinguishers — Abc Fire Extinguisher Per Exit Door, Access Box(es), |
Jeff Crawford |
8/26/2021 |
Failed: Building - Final |
Need Handrail And Gfci By Sink In Kitchen, Draftstop Stairs |
Troy Crews |
2/2/2022 |
Passed: Fire - Fire Final |
|
Lance Hill |
2/14/2022 |
Passed: Building - Final |
Items Corrected Will Request Zoning Final For C.o. |
Troy Crews |
2/28/2022 |
Failed: Engineering - Zoning Final |
See Zoning Final Inspection Performed On August 26, 2021. Site Was Not Constructed In Accordance With The Approved Site Plan. Millings Must Be Removed In Areas Required To Be Paved And The Proper Grading And Paving Must Be Perform. Additional Comments May Be Made Once Site Is Presented And Able To Be Completely Inspected. The Subject Property Is Completely Gated And Fences. Access To Site Was Not Able To Be Obtained. In The Future, A Reinspection Fee Shall Apply. If The Site Is Not Accessible At The Time Of Inspection, No Inspection Shall Be Performed. Each Reinspection Will Be Charged The $50 Reinspection Fee. |
Brandon Stubbs |
3/2/2022 |
Passed: Engineering - Zoning Final |
|
Troy Crews |
8/4/2022 |
Passed: Building - Final |
|
Troy Crews |
8/4/2022 |