Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
8/19/2020 |
Passed: Building - Footer |
Put Ground Wire On Footer Steel Prior To Pour |
Troy Crews |
2/26/2021 |
Passed: Engineering - Setbacks |
|
Troy Crews |
2/26/2021 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
3/30/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Need Toilet On Site Prior To Any More Inspections |
Troy Crews |
3/30/2021 |
Passed: Building - Slab |
Fibermesh Concrete |
Matt Forsyth |
4/21/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
10/15/2021 |
Rescheduled 10/18/2021:Building - Framing |
|
Matt Forsyth |
10/15/2021 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
10/15/2021 |
Failed: Building - Framing |
Calling For Lt19 Strapping Bottom Of Kingpost Garage Door Header Two Each Side |
Matt Forsyth |
10/18/2021 |
Passed: Building - Framing |
|
Matt Forsyth |
11/22/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
11/22/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
11/22/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
11/22/2021 |
Passed: Building - Lath/Stucco |
|
Troy Crews |
3/1/2022 |
Passed: Electrical - Permanent Power |
Need Septic And Driveway Release |
Matt Forsyth |
7/15/2022 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
7/19/2022 |
Release to power company |
|
Melissa Garber |
7/25/2022 |
Septic Release Inspection |
|
Health Dept |
7/25/2022 |
Rescheduled 9/7/2022:Building - Final |
|
Matt Forsyth |
9/6/2022 |
Failed: Building - Final |
Fresh Makeup Air Needed For Hvac And Final Termite Treatment |
Matt Forsyth |
9/7/2022 |
Passed: Building - Final |
Make Up Air Confirmed |
Matt Forsyth |
10/21/2022 |