| Passed: Building - Footer |
|
Troy Crews |
8/27/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/27/2020 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
8/28/2020 |
| Release to power company |
|
Troy Crews |
8/28/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
9/9/2020 |
| Passed: Building - Slab |
|
Troy Crews |
9/15/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
10/15/2020 |
| Passed: Building - Framing |
|
Troy Crews |
10/15/2020 |
| Passed: Building - Roof Decking |
|
Troy Crews |
10/15/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
10/30/2020 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
10/30/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
10/30/2020 |
| Passed: Building - Insulation |
|
Troy Crews |
11/12/2020 |
| Passed: Electrical - Permanent Power |
Need Final Septic Release |
Troy Crews |
1/15/2021 |
| Septic Release Inspection |
|
Health Dept |
1/19/2021 |
| Release to power company |
Eh Rec'd. |
Troy Crews |
1/20/2021 |
| Passed: Building - Final |
Release Pending Final Termite |
Troy Crews |
2/26/2021 |
| Certificate-Release Certificate |
Termite Final Received |
Troy Crews |
3/1/2021 |