Permit Details

Permit Search

Permit

New Residential Construction

316 SW YULAN ST, UNITS 100 & 102
FORT WHITE, FL 32038

Permit #
000040307
Application #
46698
Status Completed
  1. Submitted Jul 6, 2020
  2. Issued Aug 6, 2020
  3. Expires Jun 12, 2021
  4. Completed Dec 14, 2020

Property

Parcel #
14455-000
Owner
Crb Investment Properties Llc
Acres
1.01
Subdivision
—
Zoning
FORT WHITE
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
FORT WHITE
Fema map number
12023C0490C
This is the construction of a
Duplex
If Other, explain the use of the structure.
Ft White
Heated Area (Sqft)
2006
Total Area (Sqft)
2188
Stories
1
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
MULTI-FAMILY
Septic# (00-0000) or (X00-000)
20-0464
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code

Status & Review History

  1. Application pending.
  2. Application Converted
  3. Zoning Review - Reviewed
  4. Point Review - Printed-Online Application
  5. Plan Review - Documents Required
  6. Plan Review - On Hold-Incomplete
  7. Plan Review - Processing
  8. Final Review - Documents Required
  9. Zoning Review - Reviewed
  10. Plan Review - Documents Required
  11. Plan Review - Reviewed
  12. Final Review - Payment Needed
  13. Permit Issued

Contractors

  • Isaiah Cully

    Ic Construction Llc

    License
    CBC1259655
    Title
    Building Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Aug 19, 2020

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  2. Aug 19, 2020

    Release to power company

    Inspected by Matt Forsyth

  3. Aug 19, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  4. Aug 25, 2020

    Passed: Building - Monolithic Slab

    Inspected by Matt Forsyth

  5. Aug 25, 2020

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  6. Oct 5, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  7. Oct 5, 2020

    Passed: Building - Fire Rated Wall

    Inspected by Matt Forsyth

  8. Oct 5, 2020

    Passed: Building - Framing

    Inspected by Matt Forsyth

  9. Oct 5, 2020

    Passed: Building - Strapping

    Inspected by Matt Forsyth

  10. Oct 13, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  11. Oct 13, 2020

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  12. Oct 13, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  13. Oct 15, 2020

    Passed: Building - Insulation

    Walls Only

    Inspected by Matt Forsyth

  14. Nov 24, 2020

    Septic Release Inspection

    Inspected by Health Dept

  15. Nov 24, 2020

    Passed: Electrical - Permanent Power

    Temp Wires Need To Be Removed

    Inspected by Matt Forsyth

  16. Nov 24, 2020

    Release to power company

    Inspected by Matt Forsyth

  17. Dec 14, 2020

    Passed: Building - Final

    Inspected by Matt Forsyth

Documents