| Application #: | 46562 |
| Permit #: |
000040166 |
| Related Permit: |
|
| Submitted: | Monday, June 22, 2020 |
| Issued: | Friday, July 17, 2020 |
| Expires: | Friday, January 8, 2021 |
| Completed: | Friday, January 8, 2021 |
| Status: |
Completed |
| Septic Release? |
Yes |
| Elevation regulation |
Minimum Requirement |
| Finished floor requirement |
One foot above the road |
| Fema map number |
12023C0395C |
| This is the construction of a |
Single Family Dwelling |
| Setbacks Front |
30 |
| Setback Side 1 |
25 |
| Setback Side 2 |
25 |
| Setbacks Rear |
25 |
| Stories |
1 |
| Heated Area (Sqft) |
2099 |
| Total Area (Sqft) |
3311 |
| Building Height |
23 |
| Building Code Construction Type |
V |
| Building Code Element |
B |
| Building Code Occupancy Types |
Residential |
| Occupancy Use Title |
single family |
| Building Code Edition |
Florida Building Code 2017 6th Edition & 2014 National Electrical Code |
| Septic# (00-0000) or (X00-000) |
20-0536 |
| 6/22/2020 |
Application pending. |
| 6/23/2020 |
Point Review - Printed-Online Application |
| 6/23/2020 |
Point Review - Processing |
| 6/26/2020 |
Plan Review - Reviewed |
| 6/29/2020 |
Zoning Review - Reviewed |
| 7/13/2020 |
Final Review - Complete |
| 7/13/2020 |
Final Review - Payment Needed |
| 7/17/2020 |
Permit Issued |
| 12/15/2020 |
Final Review - Payment Needed |
| Name / Business |
License |
Title |
Role |
Kevin L Bedenbaugh Jr Plumb Level Construction Co Llc
|
CGC1516042 |
General Contractor |
Contractor |
Timothy D Shatto Shatto Heating & Air, Inc.
|
CAC057875 |
A/c Class B |
Subcontractor |
Ryan C Beville Rbi Electrical Contracting Llc
|
EC13004236 |
Electrical Contractor |
Subcontractor |
Mark A Ganskop Express Plumbing Inc
|
CFC1428040 |
Plumbing Contractor |
Subcontractor |
Kevin L Bedenbaugh Jr Plumb Level Construction Co Llc
|
CCC1329482 |
Roofing Contractor |
Subcontractor |
| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
Need Permit Posted On Site |
Matt Forsyth |
7/23/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
7/23/2020 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
8/5/2020 |
| Release to power company |
|
Matt Forsyth |
8/5/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
8/7/2020 |
| Passed: Building - Slab |
|
Matt Forsyth |
8/13/2020 |
| Passed: Building - Roof Decking |
|
Troy Crews |
9/1/2020 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
9/1/2020 |
| Passed: Building - Framing |
|
Matt Forsyth |
9/17/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
9/17/2020 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
9/17/2020 |
| Failed: Plumbing/Gas - 2nd Rough-In |
Vent Pipe Not Complete In Two Places |
Matt Forsyth |
9/17/2020 |
| Passed: Building - Strapping |
|
Matt Forsyth |
9/17/2020 |
| Passed: Building - Insulation |
|
Matt Forsyth |
9/24/2020 |
| Septic Release Inspection |
|
Health Dept |
12/2/2020 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
12/17/2020 |
| Release to power company |
|
Matt Forsyth |
12/17/2020 |
| Passed: Building - Final |
|
Matt Forsyth |
1/8/2021 |