| Septic Release Inspection |
|
Health Dept |
7/6/2020 |
| Passed: Building - Footer |
|
Troy Crews |
7/14/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
7/14/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Tommy Matthews |
7/23/2020 |
| Rescheduled 7/28/2020:Building - Monolithic Slab |
|
Janice Williams |
7/27/2020 |
| Rescheduled 7/28/2020:Building - Slab |
|
Janice Williams |
7/27/2020 |
| Passed: Building - Slab |
|
Troy Crews |
7/28/2020 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
7/28/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
7/28/2020 |
| Passed: Building - Roof Decking |
|
Troy Crews |
9/3/2020 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
9/3/2020 |
| Passed: Building - Framing |
|
Troy Crews |
9/28/2020 |
| Passed: Building - Strapping |
|
Troy Crews |
9/28/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
9/28/2020 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
9/28/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
9/28/2020 |
| Passed: Building - Insulation |
|
Troy Crews |
10/1/2020 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
11/12/2020 |
| Release to power company |
|
Matt Forsyth |
11/12/2020 |
| Passed: Building - Final |
|
Matt Forsyth |
1/5/2021 |