Passed: Electrical - Temporary Service |
|
Tommy Matthews |
7/21/2020 |
Release to power company |
|
Tommy Matthews |
7/21/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Keep Water Supply Pipes At Least 3/4 Inch Off Form Boards |
Tommy Matthews |
7/21/2020 |
Passed: Building - Slab |
|
Tommy Matthews |
7/30/2020 |
Passed: Electrical - 1st Underground Rough–In |
|
Tommy Matthews |
7/30/2020 |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
8/4/2020 |
Passed: Building - Lintel/Tie Beam |
Inspection For Safe Room Only. |
Tommy Matthews |
8/7/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
9/1/2020 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
9/1/2020 |
Passed: Building - Framing |
Reminder A Lot Of Truss Engineering And Strapping To Do On Interior For Framing Inspection |
Troy Crews |
9/18/2020 |
Passed: Building - Framing |
|
Troy Crews |
9/24/2020 |
Passed: Building - Strapping |
|
Troy Crews |
9/24/2020 |
Passed: Mechanical - Rough In |
|
Troy Crews |
9/24/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
9/24/2020 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
9/24/2020 |
Cancelled: Electrical - 2nd Rough-In |
|
Troy Crews |
9/29/2020 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
9/30/2020 |
Passed: Building - Insulation |
|
Troy Crews |
10/6/2020 |
Passed: Electrical - Permanent Power |
Need Final Septic And Final Driveway |
Troy Crews |
11/18/2020 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
11/19/2020 |
Release to power company |
|
Melissa Garber |
11/24/2020 |
Septic Release Inspection |
Driveway Released 11/19 |
Health Dept |
11/24/2020 |
Passed: Building - Final |
|
Anthony Aslan |
3/4/2021 |