Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
6/26/2020 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
7/1/2020 |
Release to power company |
|
Troy Crews |
7/1/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
8/7/2020 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
8/21/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
8/21/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
10/9/2020 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
10/9/2020 |
Passed: Mechanical - Rough In |
|
Troy Crews |
11/19/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
11/19/2020 |
Failed: Building - Framing |
Check Jacks And Kings On Headers, Complete Post Connection At Back Car Shelter |
Troy Crews |
11/19/2020 |
Passed: Building - Framing |
|
Troy Crews |
12/2/2020 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
12/2/2020 |
Passed: Building - Insulation |
|
Troy Crews |
12/10/2020 |
Failed: Electrical - Permanent Power |
Need Door Locks, Need Elevation Letter, Need Driveway Final From Public Works, Need Septic Final From Health Dept. |
Troy Crews |
2/15/2021 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
3/24/2021 |
Septic Release Inspection |
|
Health Dept |
3/25/2021 |
Passed: Electrical - Permanent Power |
Locks Installed Per Contractor |
Troy Crews |
4/7/2021 |
Release to power company |
|
Troy Crews |
4/7/2021 |
Passed: Building - Final |
Need To Load In Blower Door Test And Termite Final Also Assessment Fees-- All Rec'd 4/15 |
Troy Crews |
4/12/2021 |
Certificate-Release Certificate |
|
Troy Crews |
4/15/2021 |