Permit Details

Permit Search

Permit

New Residential Construction

650 SW ROCK WAY
FORT WHITE, FL 32038

Permit #
000039994
Application #
46482
Status Completed
  1. Submitted —
  2. Issued Jun 22, 2020
  3. Expires Jul 26, 2021
  4. Completed Jan 27, 2021

Property

Parcel #
09931-002
Owner
Burk Donald A & Denise R
Acres
8.52
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0495C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
2188
Total Area (Sqft)
3186
Building Height
23
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
20-0467

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Zoning Review - Reviewed
  3. Plan Review - Documents Required
  4. Zoning Review - Reviewed
  5. Permit Issued

Contractors

  • Corey J Amira

    Amira Custom Homes, Inc.

    License
    CRC1331309
    Title
    Cert. Residential
    Role
    Contractor
  • Ryan C Beville

    Rbi Electrical Contracting Llc

    License
    EC13004236
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Robert M Bounds

    Bounds Heating & Air Inc

    License
    CAC057642
    Title
    Class A A/c
    Role
    Subcontractor
  • James Butler Jr

    Butler Plumbing Of Gainesville Inc

    License
    CFC057960
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • David J Pabst

    Whittle Roofing Company, Inc.

    License
    CCC1326372
    Title
    Cert. Roofing
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Jul 6, 2020

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  2. Jul 6, 2020

    Release to power company

    Inspected by Troy Crews

  3. Jul 9, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Aug 10, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Aug 10, 2020

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Sep 3, 2020

    Rescheduled 9/8/2020:Building - Roof Decking

    Inspected by Janice Williams

  7. Sep 3, 2020

    Rescheduled 9/8/2020:Building - Wall Sheathing

    Inspected by Janice Williams

  8. Sep 8, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  9. Sep 8, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  10. Sep 18, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  11. Sep 18, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Sep 18, 2020

    Passed: Building - Strapping

    Inspected by Troy Crews

  13. Oct 6, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  14. Oct 6, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Oct 6, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  16. Oct 14, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  17. Nov 18, 2020

    Passed: Electrical - Permanent Power

    Need Final Septic

    Inspected by Troy Crews

  18. Dec 21, 2020

    Release to power company

    Rec'd. Eh

    Inspected by Troy Crews

  19. Dec 21, 2020

    Septic Release Inspection

    Inspected by Health Dept

  20. Jan 27, 2021

    Passed: Building - Final

    Inspected by Anthony Aslan

Documents