Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Special Foundation |
Troy Crews |
6/25/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
6/25/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
7/30/2020 |
Passed: Building - Slab |
|
Troy Crews |
8/17/2020 |
Failed: Building - Framing |
Check All Trusses Above 500 Pounds Uplift For Strapping, No Straps On Porch Post, Headers Above 6ft Require Larger Header Possible Letter From Engineer |
Troy Crews |
9/18/2020 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
9/18/2020 |
Passed: Mechanical - Rough In |
|
Troy Crews |
9/18/2020 |
Failed: Plumbing/Gas - 2nd Rough-In |
Not Started |
Troy Crews |
9/18/2020 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
10/14/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
10/14/2020 |
Failed: Building - Insulation |
Need Drawing For Added Dormer, Need To Close Unused Ridge Vent Decking, Do Not Drywall Until Re Inspection |
Troy Crews |
12/1/2020 |
Failed: Building - Framing |
Need Drawing For Added Dormer, Need To Pull Shingles And Close Unused Cut Out For Ridge Vent |
Troy Crews |
1/21/2021 |
Passed: Building - Strapping |
|
Troy Crews |
1/21/2021 |
Cancelled: Mechanical - Rough In |
|
Troy Crews |
1/21/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
1/21/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/21/2021 |
Passed: Building - Framing |
Ridge Has Been Filled In With 2x4 Lumber |
Troy Crews |
1/26/2021 |
Passed: Building - Insulation |
Items Corrected |
Troy Crews |
1/26/2021 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
6/3/2021 |
Release to power company |
|
Troy Crews |
6/3/2021 |
Cancelled: Building - Framing |
|
Troy Crews |
7/9/2021 |
Passed: Building - Final |
|
Troy Crews |
7/12/2021 |