Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
6/15/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
6/29/2020 |
Passed: Building - Slab |
|
Matt Forsyth |
6/29/2020 |
Cancelled: Building - Monolithic Slab |
|
Troy Crews |
7/6/2020 |
Cancelled: Engineering - Setbacks |
|
Troy Crews |
7/6/2020 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
7/6/2020 |
Release to power company |
|
Troy Crews |
7/6/2020 |
Failed: Building - Framing |
Not Ready |
Troy Crews |
7/15/2020 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
7/15/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
7/16/2020 |
Failed: Building - Framing |
Not Ready, Also Clean Trusses As Discussed With Adam. |
Troy Crews |
7/17/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
7/20/2020 |
Failed: Mechanical - Rough In |
Need Windows And Doors Installed For Further Inspections Also Clean Trusses As Discussed. |
Troy Crews |
8/7/2020 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
9/9/2020 |
Passed: Mechanical - Rough In |
Trustees Have Been Treated By Servpro |
Troy Crews |
9/9/2020 |
Passed: Building - Insulation |
|
Troy Crews |
9/10/2020 |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
10/27/2020 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
10/27/2020 |
Failed: Electrical - Permanent Power |
Need Health Release-- Rec'd 10/28, Culvert Final-- Rec'd 10/27, Elevation Confirmation Letter From Surveyor (sealed) |
Troy Crews |
10/28/2020 |
Septic Release Inspection |
Elevation Confirmation Letter From Surveyor (sealed) |
Health Dept |
10/28/2020 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
10/30/2020 |
Release to power company |
|
Troy Crews |
10/30/2020 |
Passed: Building - Final |
|
Matt Forsyth |
11/6/2020 |