Permit Details

Permit Search

Permit

New Residential Construction

204 NW SPARR LN
LAKE CITY, FL 32055

Permit #
000039846
Application #
43834
Status Completed
  1. Submitted Oct 17, 2019
  2. Issued May 29, 2020
  3. Expires Apr 18, 2021
  4. Completed Oct 21, 2020

Property

Parcel #
01720-002
Owner
Johnston Janet & Jim Inglese
Acres
0.28
Subdivision
Suwannee Valley Estates
Zoning
A-3
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0187D
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
1227
Total Area (Sqft)
1712
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0686

Status & Review History

  1. Permit Issued

Contractors

  • James H Johnston Iii

    Hometown Homes Llc

    License
    CRC1328128
    Title
    Residential Contractor
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Derrick L Williams

    Dl Williams Heating & Cooling Llc

    License
    CAC1816913
    Title
    Class "b" A/c Contractor
    Role
    Subcontractor
  • Maurice E Perkins

    M.e. Perkins Construction & Plumbing,inc.

    License
    CFC1426278
    Title
    Plumbing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Mar 19, 2020

    Septic Release Inspection

    Inspected by Health Dept

  2. Jun 2, 2020

    Passed: Building - Footer

    Inspected by Troy Crews

  3. Jun 2, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  4. Jul 1, 2020

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  5. Jul 1, 2020

    Release to power company

    Inspected by Troy Crews

  6. Jul 1, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  7. Jul 2, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  8. Jul 10, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. Jul 31, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  10. Jul 31, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  11. Jul 31, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Jul 31, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  13. Aug 4, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Oct 8, 2020

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  15. Oct 8, 2020

    Release to power company

    Inspected by Troy Crews

  16. Oct 20, 2020

    Passed: Building - Final

    Release Pending Blower Door Test And Fees

    Inspected by Troy Crews

  17. Oct 21, 2020

    Certificate-Release Certificate

    Inspected by Troy Crews