Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Troy Crews |
5/14/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
5/14/2020 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
5/28/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
5/28/2020 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
6/1/2020 |
Release to power company |
|
Troy Crews |
6/1/2020 |
Passed: Building - Slab |
|
Troy Crews |
6/2/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
Wall Sheeting Only |
Matt Forsyth |
7/21/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
7/21/2020 |
Passed: Building - Strapping |
|
Matt Forsyth |
7/22/2020 |
Failed: Building - Framing |
Check Back Over Truss Engineering, Need Repair For Truss Cut For Front Gable Window, Anchor Bolts Not Complete Including Plate Splices, Check Strapping On All Trusses Over 500 Pound Uplift, Garage Header Not Strapped And Tied At Bottom Per Plan, Girder Truss All Thread Not Installed. |
Troy Crews |
7/29/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
7/31/2020 |
Release to power company |
|
Matt Forsyth |
7/31/2020 |
Failed: Building - Framing |
Check All Uplift Over 500 For More Clips, Gable Truss North End Needs Bracing, T-06 Truss Broken Need Repair Paperwork And Repair Done, Still Need Repairs For Trusses Cut For False Gable Windows. Do Not Insulate Needs Final Framing Inspection. |
Troy Crews |
8/12/2020 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
8/12/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
8/12/2020 |
Failed: Mechanical - Rough In |
Oven Duct. Not Complete, Do Not Insulate House |
Troy Crews |
8/12/2020 |
Passed: Mechanical - Rough In |
|
Troy Crews |
8/28/2020 |
Failed: Building - Framing |
Same Framing Issues Remain |
Troy Crews |
8/28/2020 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
9/4/2020 |
Passed: Building - Insulation |
|
Troy Crews |
9/4/2020 |
Septic Release Inspection |
|
Health Dept |
10/14/2020 |
Rescheduled 10/30/2020:Electrical - Permanent Power |
|
Troy Crews |
10/29/2020 |
Failed: Electrical - Permanent Power |
Meter Can Needs Temp Wires Removed From Main Lugs |
Matt Forsyth |
10/30/2020 |
Passed: Electrical - Permanent Power |
Meter Can Adjusted |
Matt Forsyth |
11/2/2020 |
Release to power company |
|
Matt Forsyth |
11/2/2020 |
Failed: Building - Final |
Need Setback Letter Confirmation- Rec'd |
Matt Forsyth |
11/9/2020 |
Passed: Building - Final |
|
Matt Forsyth |
11/10/2020 |