Permit Details

Permit Search

Permit

New Residential Construction

449 SW SUMMERHILL GLN
LAKE CITY, FL 32024

Permit #
000039735
Application #
44753
Status Completed
  1. Submitted —
  2. Issued May 5, 2020
  3. Expires Mar 2, 2021
  4. Completed Sep 3, 2020

Property

Parcel #
03455-017
Owner
Timothy & Alison Strachan
Acres
1.01
Subdivision
—
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0379C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
1704
Total Area (Sqft)
2390
Building Height
17
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
20-0220

Status & Review History

  1. Zoning Review - Completed/Sent for Final Review
  2. Permit Issued

Contractors

  • Jason Huddleston

    Red Door Homes Of North Central Florida Llc

    License
    CBC1262184
    Title
    Cert. Building
    Role
    Contractor

    County License Expired.

  • Ryan C Beville

    Rbi Electrical Contracting Llc

    License
    EC13004236
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Erik W Worthmann

    Comfort Temp Company/dba Ct Mechanical

    License
    CMC1249305
    Title
    Cert. Mechanical
    Role
    Subcontractor

    County License & State License Expired.

  • Robert A Faulkner

    Premier Plumbing & Leak Detection

    License
    CFC1426552
    Title
    Cert Plumbing
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. May 8, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Need Compaction Test Done On Footings

    Inspected by Matt Forsyth

  2. May 20, 2020

    Failed: Building - Monolithic Slab

    Need Density Test On Footings

    Inspected by Matt Forsyth

  3. May 20, 2020

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  4. May 20, 2020

    Failed: Electrical - Footer Steel & Grounding

    Inspected by Matt Forsyth

  5. May 21, 2020

    Passed: Building - Monolithic Slab

    Density Test Received

    Inspected by Matt Forsyth

  6. May 21, 2020

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  7. Jun 4, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  8. Jun 4, 2020

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  9. Jul 15, 2020

    Failed: Building - Framing

    Headers Need To Be Nailed Off 12 Inches On Center

    Inspected by Matt Forsyth

  10. Jul 15, 2020

    Passed: Building - Strapping

    Inspected by Matt Forsyth

  11. Jul 15, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  12. Jul 15, 2020

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  13. Jul 15, 2020

    Failed: Plumbing/Gas - 2nd Rough-In

    Not Completed

    Inspected by Matt Forsyth

  14. Jul 15, 2020

    Failed: Plumbing/Gas - Tub Set/Shower Pan

    Not Complete

    Inspected by Matt Forsyth

  15. Jul 17, 2020

    Failed: Building - Framing

    Headers Not Nailed Properly

    Inspected by Matt Forsyth

  16. Jul 17, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  17. Jul 20, 2020

    Passed: Building - Framing

    Inspected by Matt Forsyth

  18. Jul 20, 2020

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  19. Jul 22, 2020

    Passed: Building - Insulation

    Walls Only

    Inspected by Matt Forsyth

  20. Aug 18, 2020

    Cancelled: Electrical - Permanent Power

    Inspected by Matt Forsyth

  21. Aug 18, 2020

    Cancelled: Electrical - Permanent Power

    Inspected by Matt Forsyth

  22. Aug 21, 2020

    Septic Release Inspection

    Inspected by Health Dept

  23. Aug 24, 2020

    Failed: Electrical - Permanent Power

    Metercan Work Not Complete

    Inspected by Matt Forsyth

  24. Aug 26, 2020

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  25. Aug 26, 2020

    Release to power company

    Inspected by Matt Forsyth

  26. Sep 3, 2020

    Passed: Building - Final

    Contractor To Check Front And Rear Porch Gfi's Also Garage Plug For Freezer Change To Single Outlet

    Inspected by Troy Crews

Documents