Failed: Building - Framing
1) Header Not As Per Plan Over Rear Glass Sliding Door.
2) Rear Wall Calls For Shear Transfer
3) Girder T-11 Needs 3-2x6 Studs Under Back End Of Truss And Htt4 At Base.
4) Two Interior Shearwalls Need Sheathing One Side.
5) Balloon Frame Walls Require Blocking Between Trusses.
6) Girder T-19 Need Additional Hold Down (2) H2.5 On One End.
(7) T-5,6,7,8,12,13,14 & 15 Needs Additional Hold Down Each End.
Inspected by Tommy Matthews