Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
4/29/2020 |
Passed: Engineering - Setbacks |
Need Portalet For Next Inspection |
Matt Forsyth |
4/29/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
5/18/2020 |
Passed: Building - Slab |
|
Troy Crews |
5/26/2020 |
Failed: Building - Roof Decking |
Cover But Remove Shiners And Look Again At Framing |
Tommy Matthews |
6/30/2020 |
Failed: Building - Wall Sheathing |
Remove And Replace Shiners. |
Tommy Matthews |
6/30/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
7/16/2020 |
Failed: Building - Framing |
All Headers Nailed 12"on Center Top And Bottom. |
Matt Forsyth |
7/16/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
7/16/2020 |
Passed: Building - Strapping |
|
Matt Forsyth |
7/16/2020 |
Failed: Building - Framing |
Beams On Porch And Lvl In Garage Nailed 12" Oc Both Sides Top And Bottom (face).anchor Bolt Nut Missing In Garage.need Safety Railing On Staircase. |
Matt Forsyth |
8/20/2020 |
Failed: Electrical - 2nd Rough-In |
Need Nail Plates In Following Areas;service Entrance,double Oven,hall Bath |
Matt Forsyth |
8/20/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
8/20/2020 |
Failed: Plumbing/Gas - 2nd Rough-In |
Nail Plates For Gas And Waste Pipe In Kitchen Master Bath And Entry. Water On Waste Pipe Notied Will It Hold In Bathtub?(second Floor) |
Matt Forsyth |
8/20/2020 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
9/2/2020 |
Passed: Building - Insulation |
|
Troy Crews |
9/2/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
Items Corrected |
Troy Crews |
9/2/2020 |
Failed: Electrical - Permanent Power |
Electrical Work Not Done To Release Power |
Matt Forsyth |
10/8/2020 |
Rescheduled 10/9/2020:Electrical - Permanent Power |
|
Troy Crews |
10/8/2020 |
Cancelled: Engineering - Final Driveway |
Waiver Permit Converted To A Culvert Permit. That Had Already Been Installed. |
Melissa Garber |
10/8/2020 |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
10/9/2020 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
10/9/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
10/9/2020 |
Release to power company |
Culvert Permit Approved 10.9.20 |
Matt Forsyth |
10/9/2020 |
Passed: Electrical - Permanent Power |
Need Septic Released |
Matt Forsyth |
11/18/2020 |
Septic Release Inspection |
|
Health Dept |
11/20/2020 |
Release to power company |
|
Melissa Garber |
11/23/2020 |
Failed: Building - Final |
Work On Home Needs To Finished |
Matt Forsyth |
12/9/2020 |
Passed: Building - Final |
Waiting On Chad For Ground Engineering |
Matt Forsyth |
12/11/2020 |
Certificate-Release Certificate |
County Engineer Has Approved T.c. |
Matt Forsyth |
1/12/2021 |