Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Tommy Matthews |
5/8/2020 |
Passed: Engineering - Setbacks |
|
Tommy Matthews |
5/8/2020 |
Failed: Electrical - 1st Underground Rough–In |
Need Me Notarize Letter From Plumber For Underground Work |
Matt Forsyth |
5/29/2020 |
Passed: Building - Slab |
|
Matt Forsyth |
6/3/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
6/3/2020 |
Release to power company |
|
Matt Forsyth |
6/3/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
Wall Sheeting Only Ok To Cover |
Matt Forsyth |
7/17/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
7/17/2020 |
Passed: Building - Framing |
Need Safety Railing On Stairway |
Matt Forsyth |
8/3/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
9/21/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
9/21/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
Need Nail Plates For Gas Line Two Places |
Matt Forsyth |
9/21/2020 |
Passed: Building - Insulation |
|
Matt Forsyth |
10/5/2020 |
Septic Release Inspection |
|
Health Dept |
3/16/2021 |
Failed: Electrical - Permanent Power |
No Work Inside Until Proper Safety Railing Installed |
Matt Forsyth |
4/5/2021 |
Passed: Electrical - Permanent Power |
Safety Railing Installed |
Matt Forsyth |
4/6/2021 |
Release to power company |
|
Matt Forsyth |
4/6/2021 |
Failed: Building - Final |
Front Door Gfci Not Correct, Upstairs West Bathroom Gfci Not Correct, Cabinets Not Complete Could Not Test Kitchen Gfci Plugs, Small Deck At Rear Patio Will Need To Be Tapered 2inch Step Up, 4inches Is Minimum Step, Need Blower Door Test, Also Stair Guardrail Not Complete |
Troy Crews |
5/26/2021 |
Passed: Building - Final |
|
Matt Forsyth |
5/28/2021 |