Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
4/21/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/21/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
4/30/2020 |
Passed: Building - Slab |
|
Matt Forsyth |
5/6/2020 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
6/23/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
7/2/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
7/2/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
7/2/2020 |
Failed: Electrical - 2nd Rough-In |
Need Nail Plates Above Electric Panel |
Matt Forsyth |
7/30/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
7/30/2020 |
Failed: Plumbing/Gas - 2nd Rough-In |
Need Nail Plate In Master Shower |
Matt Forsyth |
7/30/2020 |
Passed: Building - Insulation |
|
Matt Forsyth |
8/18/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
8/18/2020 |
Failed: Plumbing/Gas - 2nd Rough-In |
Still Missing Nail Plate In Master Shower(overhead Shower Is Not Protected Coming Thru Double Top Plate |
Matt Forsyth |
8/18/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
8/19/2020 |
Failed: Electrical - Permanent Power |
Electrical Service Not Built Romex Not Safe Hanging Out Of Ele Boxes Need Wire Nuts Need. Driveway And Septic Releases |
Matt Forsyth |
10/7/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
10/7/2020 |
Release to power company |
|
Matt Forsyth |
10/7/2020 |
Release to power company |
Corrected The Power Company And Resent |
Laurie Hodson |
10/8/2020 |
Release to power company |
Corrected Power Comp |
Matt Forsyth |
10/13/2020 |
Septic Release Inspection |
|
Health Dept |
10/14/2020 |
Passed: Electrical - Permanent Power |
Need Driveway Release To Release Power |
Matt Forsyth |
11/25/2020 |
Release to power company |
|
Melissa Garber |
12/2/2020 |
Certificate-Release Certificate |
|
Matt Forsyth |
12/16/2020 |
Passed: Building - Final |
|
Matt Forsyth |
12/16/2020 |