Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Troy Crews |
3/26/2020 |
Passed: Engineering - Setbacks |
|
Troy Crews |
3/26/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
4/13/2020 |
Passed: Building - Slab |
|
Troy Crews |
4/23/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
Wall Sheeting Only |
Troy Crews |
5/12/2020 |
Failed: Building - Framing |
Not Ready |
Troy Crews |
5/12/2020 |
Failed: Building - Strapping |
Need To Strap Gable Ends And Also All Porch Post Have Not Been Strapped |
Troy Crews |
5/12/2020 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
5/28/2020 |
Passed: Building - Strapping |
|
Troy Crews |
5/28/2020 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
5/28/2020 |
Passed: Mechanical - Rough In |
|
Troy Crews |
5/28/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
5/28/2020 |
Failed: Building - Framing |
T-04truss Broken Need Paperwork From Truss Company And Repair Done,interior Header Calls For 4ply Lvl Only Has 2, T-04truss On Bottom Needs Strapping ,t-17truss Needs Strapping, All Truss Bearing Points On Porches Need Simpson Screws Must Be Re Inspected Prior To Insulation.
|
Troy Crews |
5/29/2020 |
Cancelled: Electrical - 2nd Rough-In |
Already Done |
Troy Crews |
6/22/2020 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
Already Done |
Troy Crews |
6/22/2020 |
Cancelled: Building - Wall Sheathing |
Already Done
|
Troy Crews |
6/22/2020 |
Cancelled: Mechanical - Rough In |
Already Done |
Troy Crews |
6/22/2020 |
Cancelled: Building - Strapping |
Already Done |
Troy Crews |
6/22/2020 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
Already Done |
Troy Crews |
6/22/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
6/22/2020 |
Failed: Building - Framing |
Front Porch Trusses Not Attached With Simpson Screws, 4 Ply Entry Girder Straps Not Re Attached. Call Framing Back In With Wall Insulation. |
Troy Crews |
6/23/2020 |
Passed: Building - Insulation |
|
Troy Crews |
6/29/2020 |
Failed: Electrical - Permanent Power |
Need Doors, Door Locks, Garage Door, Also Before Final Air Handler Needs To Be Sealed To Ductboard In Rear Of Unit |
Troy Crews |
12/1/2020 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
1/28/2021 |
Release to power company |
|
Troy Crews |
1/28/2021 |
Failed: Building - Final |
Right Hand Side Of Double Vanity Master Bath Outlet Not Working, East Side Upper Bedroom No Egress Window Both Fixed, West Side Upper Bedroom No Smoke Detector, Need Blower Door Test |
Troy Crews |
2/10/2021 |
Failed: Building - Final |
Outlet To Right Side Of Master Sink Still Not Working, No Smoke Detector In West Side Bedroom Upstairs, Hinges And Clothes Closet In East Side Room Upstairs With Fixed Windows |
Troy Crews |
2/19/2021 |
Passed: Building - Final |
Outlet To Far Right Of Double Vanity Still Not Functional, Repair Prior To Delivery |
Troy Crews |
2/23/2021 |