Permit Details

Permit Search

Permit

New Residential Construction

106 SW JACK GLN
LAKE CITY, FL 32024

Permit #
000039322
Application #
44425
Status Completed
  1. Submitted —
  2. Issued Feb 20, 2020
  3. Expires Nov 29, 2020
  4. Completed Jun 2, 2020

Property

Parcel #
03116-042
Owner
George & Christine Magalhaes
Acres
0.97
Subdivision
Piccadilly Park Replat Unr
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
1' ABOVE ROAD
Fema map number
12023C0381D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25
Setback Side 1
10
Setback Side 2
10
Setbacks Rear
15
Stories
1
Heated Area (Sqft)
1170
Total Area (Sqft)
1170
Building Height
13
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
Single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
20-0118

Status & Review History

  1. Zoning Review - Completed/Sent for Final Review
  2. Permit Issued

Contractors

This is an owner-builder project.

  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Feb 21, 2020

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  2. Feb 21, 2020

    Release to power company

    Inspected by Troy Crews

  3. Mar 9, 2020

    Passed: Building - Footer

    Inspected by Troy Crews

  4. Mar 9, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Mar 16, 2020

    Passed: Building - Masonry Wall Reinforcing

    Inspected by Troy Crews

  6. Mar 24, 2020

    Passed: Building - Framing

    Floor Framing

    Inspected by Troy Crews

  7. Apr 20, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Apr 20, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  9. May 6, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  10. May 6, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  11. May 6, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. May 6, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  13. May 12, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. May 14, 2020

    Release to power company

    Need To Pay Assessment Fees Before Final

    Inspected by Laurie Hodson

  15. May 14, 2020

    Passed: Electrical - Permanent Power

    Need Health Release

    Inspected by Troy Crews

  16. May 14, 2020

    Septic Release Inspection

    Inspected by Health Dept

  17. Jun 2, 2020

    Passed: Building - Final

    Inspected by Troy Crews