Permit Details

Permit Search

Permit

New Residential Construction

614 SE PRESS RUTH DR
LAKE CITY, FL 32025

Permit #
000039317
Application #
44481
Status Completed
  1. Submitted —
  2. Issued Feb 19, 2020
  3. Expires Feb 9, 2021
  4. Completed Aug 21, 2020

Property

Parcel #
08356-004
Owner
Robertson Tony E
Acres
16.32
Subdivision
—
Zoning
RSF-1
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
1' ABOVE ROAD
Fema map number
12023C0315C
This is the construction of a
Single Family Dwelling
Setbacks Front
25
Setback Side 1
10
Setback Side 2
10
Setbacks Rear
15
Stories
1
Heated Area (Sqft)
1804
Total Area (Sqft)
2300
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
Single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
20-0069

Status & Review History

  1. Point Review - Status Cleared
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Matthew A Erkinger,sr.

    Erkinger Construction Group

    License
    CRC1330825
    Title
    Residential Contractor
    Role
    Contractor

    County License & State License & Liability Insurance Expired.

  • Cody Barrs

    Barrs Plumbing,inc.

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Richard C Register

    Register's Heating & Air Conditioning,inc.

    License
    CAC041267
    Title
    Class B
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

  • Wallace W Powell

    Powell & Sons Roofing,inc.

    License
    CCC057307
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Feb 26, 2020

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Feb 26, 2020

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Mar 16, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  4. Mar 19, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Apr 17, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  6. Apr 17, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Apr 17, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  8. Apr 27, 2020

    Failed: Building - Framing

    Check Trusses Back Wall Of House Several More Need Two Clips, Call Back In With Insulation.

    Inspected by Troy Crews

  9. Apr 27, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Apr 27, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  11. Apr 27, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  12. May 5, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. May 5, 2020

    Passed: Building - Strapping

    Inspected by Troy Crews

  14. May 5, 2020

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  15. Aug 13, 2020

    Passed: Building - Final

    Need To Complete Assessment Payment For Release

    Inspected by Troy Crews

  16. Aug 20, 2020

    Release to power company

    Inspected by Melissa Garber

  17. Aug 20, 2020

    Septic Release Inspection

    Inspected by Health Dept

  18. Aug 21, 2020

    Certificate-Release Certificate

    Inspected by Troy Crews