Permit Details

Permit Search

Permit

New Residential Construction

503 NW CAMBRIDGE HILL WAY
LAKE CITY, FL 32055

Permit #
000039125
Application #
44249
Status Completed
  1. Submitted —
  2. Issued Jan 8, 2020
  3. Expires Jan 16, 2021
  4. Completed Jul 27, 2020

Property

Parcel #
01777-121
Owner
Albert & Dianne Nagy
Acres
5.08
Subdivision
Suwannee Valley Farms Phase 1
Zoning
A-3
Flood zone
A
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
102'
Fema map number
12023C0186D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
1849
Total Area (Sqft)
2634
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0929

Status & Review History

  1. Point Review - Received
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

  • Josh Sparks

    Sparks Construction

    License
    CBC1252260
    Title
    Building Contractor
    Role
    Contractor
  • Benjamin L Sparks

    Line Electric Company, Llc

    License
    EC13009101
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Stephen M Brisbois

    Epic Ac Service

    License
    CAC1819412
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing,inc.

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Ralph W Laverdure

    Rwl Roofing,llc.

    License
    CCC1328590
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jan 10, 2020

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Jan 10, 2020

    Passed: Engineering - Setbacks

    Job Site Needs Portalet

    Inspected by Matt Forsyth

  3. Jan 23, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Tommy Matthews

  4. Jan 28, 2020

    Passed: Building - Slab

    Inspected by Tommy Matthews

  5. Feb 28, 2020

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  6. Feb 28, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Check North Side For Intermediate Spacing. Nails Sunk In Too Deep. Will Renail And Cover. Will Check Again On Next Inspection.

    Inspected by Tommy Matthews

  7. Mar 5, 2020

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  8. Mar 5, 2020

    Release to power company

    Inspected by Tommy Matthews

  9. Mar 5, 2020

    Failed: Building - Framing

    Trusses Should Not Be Attached To Porch Bean, Front And Back. Girder Truss Column Detail Requires Httskt At Bottom And Lgt Girder Truss Anchor At Top. garage End Wall Detail Requires Double Bottom Plate And Wall Sheathing On Inside. Trusses Not As Per Permit Set. New Set In Permit Box Dated 2/11/20 Are Used As Permit Set Now.

    Inspected by Tommy Matthews

  10. Mar 18, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Tommy Matthews

  11. Mar 18, 2020

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  12. Mar 18, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Tommy Matthews

  13. Mar 18, 2020

    Failed: Building - Framing

    No Items Mentioned In Previous Inspection Were Addressed. If Not Addressed In Next Inspection, There Will Be A $50 Reinspection Fee Required.

    Inspected by Tommy Matthews

  14. Mar 31, 2020

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  15. Mar 31, 2020

    Passed: Building - Framing

    Need Exception For Interior Sheathing Each Side Of Garage Door.

    Inspected by Tommy Matthews

  16. May 11, 2020

    Passed: Electrical - Permanent Power

    Need Final Septic And Driveway Release

    Inspected by Troy Crews

  17. Jun 29, 2020

    Release to power company

    Inspected by Melissa Garber

  18. Jun 29, 2020

    Septic Release Inspection

    Inspected by Health Dept

  19. Jul 20, 2020

    Passed: Building - Final

    Need Elevation Certificate And Final Termite Inspection Prior To Co. Both Rec'd.

    Inspected by Tommy Matthews

  20. Jul 27, 2020

    Certificate-Release Certificate

    All Needed Doc's Rec'd

    Inspected by Tommy Matthews