Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
1/22/2020 |
Passed: Building - Monolithic Slab |
|
Matt Forsyth |
1/27/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
1/27/2020 |
Passed: Electrical - Footer Steel & Grounding |
|
Matt Forsyth |
1/27/2020 |
Passed: Building - Roof Decking |
|
Tommy Matthews |
3/5/2020 |
Failed: Building - Ext Strapping/Wall Sheathing |
Too Many Shiners. Will Check Again At Framing Inspection. Ok To Cover. |
Tommy Matthews |
3/5/2020 |
Failed: Building - Framing |
Inspection Provided But Will Not Pass Unless Deficient Items Are Taken Care Of, "strapping/wall Sheathing" Inspection Is Passed And Elevation Confirmation Letter Is Provided.
framing Items: Required Is 3 Full Height Studs Each Side Of Garage Door. See "standard Header Schedule, Sheet S-2.
need Anchor Bolts At Splice In Base Plate At Left Side Of Garage Door (outside Looking In).
truss C2 (3) Not Clipped At Front Door. |
Tommy Matthews |
3/10/2020 |
Failed: Building - Framing |
All Items Mentioned In Previous Framing Inspection Not Completed. Next Time If All Are Not Completed, There Will Be A $50 Reinspection Fee. |
Tommy Matthews |
3/12/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Tommy Matthews |
3/20/2020 |
Passed: Building - Framing |
|
Tommy Matthews |
3/20/2020 |
Failed: Electrical - 2nd Rough-In |
Smoke Detector Needs To Be At Least 3' From Ac Vent In Master Bedroom. |
Tommy Matthews |
3/20/2020 |
Passed: Mechanical - Rough In |
|
Tommy Matthews |
3/20/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
3/20/2020 |
Cancelled: Building - Framing |
|
Tommy Matthews |
3/26/2020 |
Passed: Building - Insulation |
|
Tommy Matthews |
3/26/2020 |
Passed: Electrical - 2nd Rough-In |
|
Tommy Matthews |
3/26/2020 |
Failed: Electrical - Permanent Power |
House Needs To Be Lockable. Need Conduit For Power Company Cable At Meter Can |
Tommy Matthews |
7/1/2020 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
7/10/2020 |
Release to power company |
|
Matt Forsyth |
7/10/2020 |
Failed: Building - Final |
Gfi Outlets Do Not Work In Kitchen, Baths And Laundry.
need Blower Door Test Approval.
need Final Termite Approval. |
Tommy Matthews |
8/5/2020 |
Failed: Building - Final |
Need Blower Door Test Also Hot Water Heater Needs To Be Piped To The Outside From Drain Pan |
Matt Forsyth |
9/9/2020 |
Passed: Building - Final |
|
Matt Forsyth |
9/28/2020 |