Permit Details

Permit Search

Permit

New Residential Construction

986 SW HILL CREEK DRIVE
LAKE CITY, FL 32025

Permit #
000039098
Application #
44143
Status Completed
  1. Submitted —
  2. Issued Jan 2, 2020
  3. Expires Jul 28, 2021
  4. Completed Feb 3, 2021

Property

Parcel #
09116-112
Owner
Thomas & Wendy Cushman
Acres
5.01
Subdivision
Hills At Rose Creek Phase 1
Zoning
A-3
Flood zone
A
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
1' ABOVE ROAD
Fema map number
12023C0384D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
2638
Total Area (Sqft)
4196
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0892

Status & Review History

  1. Point Review - Processing
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Jan 16, 2020

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Jan 16, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jan 31, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Feb 6, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Feb 10, 2020

    Release to power company

    Inspected by Troy Crews

  6. Feb 11, 2020

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  7. Mar 16, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  8. Mar 31, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  9. Jun 11, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  10. Jun 11, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  11. Jun 11, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Jun 11, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  13. Jun 26, 2020

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  14. Sep 22, 2020

    Passed: Electrical - Permanent Power

    Need Final Septic Release And Also Elevation Confirmation Letter

    Inspected by Troy Crews

  15. Sep 24, 2020

    Release to power company

    As Per Notes In Our System

    Inspected by Troy Crews

  16. Sep 25, 2020

    Septic Release Inspection

    Inspected by Health Dept

  17. Jan 26, 2021

    Cancelled: Electrical - Permanent Power

    Inspected by Troy Crews

  18. Jan 29, 2021

    Passed: Building - Final

    Need Surveyor Letter

    Inspected by Troy Crews