Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Tommy Matthews |
12/3/2019 |
Passed: Engineering - Setbacks |
|
Tommy Matthews |
12/3/2019 |
Failed: Electrical - Temporary Service |
Need Front Cover. Need To Seal Up Holes In Bottom Of Panel Box. Need Gfi Outlet Installed. |
Tommy Matthews |
12/3/2019 |
Passed: Electrical - Temporary Service |
|
Tommy Matthews |
12/6/2019 |
Release to power company |
|
Tommy Matthews |
12/6/2019 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Tommy Matthews |
12/12/2019 |
Passed: Building - Slab |
|
Tommy Matthews |
12/18/2019 |
Septic Release Inspection |
|
Health Dept |
1/2/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
All Strapping Is Not Complete. Do Not Cover Strapping And Will Look At It With Roof Nailing Inspection. |
Tommy Matthews |
1/13/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
1/30/2020 |
Failed: Building - Framing |
Need To Resolve Question About King Studs.
need To Resolve Question About Too Many Tie Downs For Trusses That Go Over Front And Back Porches. |
Tommy Matthews |
2/11/2020 |
Passed: Building - Framing |
|
Tommy Matthews |
2/24/2020 |
Passed: Electrical - 1st Underground Rough–In |
|
Tommy Matthews |
2/24/2020 |
Passed: Mechanical - Above Ceiling |
This Is Not Required. Should Be For Commercial Application Only. |
Tommy Matthews |
2/24/2020 |
Passed: Mechanical - Rough In |
|
Tommy Matthews |
2/24/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Tommy Matthews |
2/24/2020 |
Passed: Building - Insulation |
|
Tommy Matthews |
2/27/2020 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
4/13/2020 |
Release to power company |
|
Troy Crews |
4/13/2020 |
Passed: Building - Final |
Blower Door Results And Termite Cert Rec'd |
Tommy Matthews |
5/12/2020 |
Certificate-Release Certificate |
|
Tommy Matthews |
5/14/2020 |