| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
11/7/2019 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Keep Pipes At Least 3/4" From Form Boards. |
Tommy Matthews |
12/6/2019 |
| Passed: Engineering - Setbacks |
|
Tommy Matthews |
12/9/2019 |
| Passed: Building - Monolithic Slab |
Need Porti Potti Before Next Inspection. State Law |
Tommy Matthews |
12/9/2019 |
| Failed: Electrical - Temporary Service |
Receipts Need To Be Gfci Either By Plug Of Beaker. |
Tommy Matthews |
12/16/2019 |
| Passed: Electrical - Temporary Service |
|
Tommy Matthews |
12/18/2019 |
| Release to power company |
|
Tommy Matthews |
12/18/2019 |
| Release to power company |
|
Mg |
12/27/2019 |
| Rescheduled 2/18/2020:Electrical - 2nd Rough-In |
|
Janice Williams |
2/17/2020 |
| Failed: Building - Framing |
Misc. Items As Mention To Contractor. |
Tommy Matthews |
2/17/2020 |
| Failed: Building - Roof Decking |
Remove Shiners And Renail |
Tommy Matthews |
2/17/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Tommy Matthews |
2/17/2020 |
| Cancelled: Electrical - 2nd Rough-In |
|
Tommy Matthews |
2/17/2020 |
| Cancelled: Electrical - 2nd Rough-In |
|
Tommy Matthews |
2/19/2020 |
| Passed: Building - Framing |
|
Tommy Matthews |
2/19/2020 |
| Passed: Building - Roof Decking |
|
Tommy Matthews |
2/19/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Tommy Matthews |
2/26/2020 |
| Passed: Building - Insulation |
|
Tommy Matthews |
3/6/2020 |
| Passed: Mechanical - Rough In |
|
Tommy Matthews |
3/6/2020 |
| Passed: Electrical - Permanent Power |
|
Tommy Matthews |
5/12/2020 |
| Release to power company |
|
Tommy Matthews |
5/12/2020 |
| Passed: Building - Final |
|
Tommy Matthews |
6/18/2020 |