Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Troy Crews |
12/19/2019 |
Passed: Engineering - Setbacks |
|
Troy Crews |
12/19/2019 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
1/21/2020 |
Passed: Building - Slab |
Mirrow Image Layout Of Home. |
Tommy Matthews |
2/12/2020 |
Passed: Building - Roof Decking |
|
Troy Crews |
3/24/2020 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
3/24/2020 |
Failed: Building - Framing |
Header Schedule Calls For 2 King Studs All Headers, Anchor Bolts Not 24 Inch On Center Per Plan. Need Letter From Engineer Or Make Corrections. |
Troy Crews |
8/10/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
8/26/2020 |
Failed: Mechanical - Rough In |
Connect Bath Fans , Also Check For Ducts Crimped Several Locations. |
Troy Crews |
8/26/2020 |
Cancelled: Electrical - 1st Underground Rough–In |
|
Troy Crews |
8/26/2020 |
Failed: Electrical - 2nd Rough-In |
Need Smoke Detector Outside The 2 Northeast Bedrooms |
Troy Crews |
8/26/2020 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
8/31/2020 |
Passed: Electrical - 2nd Rough-In |
Smoke Detector Added |
Troy Crews |
8/31/2020 |
Passed: Mechanical - Rough In |
Items Corrected |
Troy Crews |
8/31/2020 |
Passed: Building - Insulation |
|
Troy Crews |
9/14/2020 |
Failed: Electrical - Permanent Power |
Need Wire Nuts On Romex Wire Plug On Panel Inside |
Matt Forsyth |
3/8/2021 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
3/9/2021 |
Release to power company |
|
Melissa Garber |
3/16/2021 |
Septic Release Inspection |
|
Health Dept |
3/16/2021 |
Failed: Building - Final |
Need Blower Door Test Also Receptacle Under Sink Not In Approved Bo |
Matt Forsyth |
4/29/2021 |
Passed: Building - Final |
|
Matt Forsyth |
6/14/2021 |