Permit Details

Permit Search

Permit

New Residential Construction

816 SW HEFLIN AVE
FORT WHITE, FL 32038

Permit #
000038878
Application #
43856
Status Completed
  1. Submitted Oct 21, 2019
  2. Issued Nov 8, 2019
  3. Expires Nov 18, 2020
  4. Completed May 22, 2020

Property

Parcel #
10058-675
Owner
Reginald & Regina Crutchfield
Acres
1.63
Subdivision
Santa Fe River Plantations Replat Of Lots 38,45,46
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
46
Fema map number
12023C0532C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
50
Setback Side 1
50
Setback Side 2
50
Setbacks Rear
50
Stories
1
Heated Area (Sqft)
2110
Total Area (Sqft)
3285
Building Height
16
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0788

Status & Review History

  1. Zoning Review - Processing
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

  • Joel G Buzbee

    G Buzbee, Inc

    License
    CGC061980
    Title
    Cert General
    Role
    Contractor

    County License & State License Expired.

  • Chad White

    Ck Electric Llc

    License
    EC13002222
    Title
    Electrical Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • Donald Davis

    High Springs Electric Inc.

    License
    EC0002306
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Paul K Coleman

    Coleman's Plumbing Inc.

    License
    CFC1425624
    Title
    Certified Plumbing
    Role
    Subcontractor

    County License & State License & Employees Workers Comp Expired.

Inspections

  1. Nov 12, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  2. Nov 12, 2019

    Release to power company

    Inspected by Tommy Matthews

  3. Nov 18, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  4. Nov 18, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Nov 18, 2019

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Troy Crews

  6. Dec 6, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Tommy Matthews

  7. Dec 12, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  8. Dec 12, 2019

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Tommy Matthews

  9. Jan 17, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  10. Jan 17, 2020

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  11. Feb 19, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Tommy Matthews

  12. Feb 19, 2020

    Passed: Mechanical - Above Ceiling

    Inspected by Tommy Matthews

  13. Feb 19, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Tommy Matthews

  14. Feb 19, 2020

    Failed: Building - Framing

    Clips For Truss To Beam For Porches Covered Up.

    Inspected by Tommy Matthews

  15. Feb 19, 2020

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  16. Feb 20, 2020

    Passed: Building - Framing

    Inspected by Tommy Matthews

  17. Feb 26, 2020

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  18. Apr 7, 2020

    Failed: Electrical - Permanent Power

    Need Conduit Run To The Meter Can.need Septic Release.need Garage Door Installed.

    Inspected by Matt Forsyth

  19. Apr 8, 2020

    Septic Release Inspection

    Inspected by Health Dept

  20. Apr 9, 2020

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  21. Apr 9, 2020

    Release to power company

    Inspected by Matt Forsyth

  22. May 22, 2020

    Passed: Building - Final