Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
|
Tommy Matthews |
11/26/2019 |
Release to power company |
|
Tommy Matthews |
11/26/2019 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Tommy Matthews |
12/10/2019 |
Passed: Building - Slab |
|
Tommy Matthews |
12/16/2019 |
Septic Release Inspection |
|
Health Dept |
1/9/2020 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
1/28/2020 |
Passed: Building - Roof Decking |
|
Tommy Matthews |
1/28/2020 |
Passed: Building - Framing |
Window Nail Off Only |
Matt Forsyth |
1/31/2020 |
Passed: Building - Framing |
Framing Was For Exterior Door Fasteners Only |
Matt Forsyth |
2/5/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
2/26/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
2/26/2020 |
Passed: Mechanical - Above Ceiling |
|
Matt Forsyth |
2/26/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
2/26/2020 |
Failed: Plumbing/Gas - 2nd Rough-In |
Bathtub Needs To Be Reset Leaking |
Matt Forsyth |
2/26/2020 |
Failed: Building - Insulation |
Need Bathtub Reinspected Before Any Other Inspections |
Matt Forsyth |
3/9/2020 |
Passed: Building - Insulation |
|
Tommy Matthews |
3/11/2020 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Tommy Matthews |
3/11/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Tommy Matthews |
3/11/2020 |
Cancelled: Building - Rated Assembly Fastening |
Drywall Inspection Not Needed, Check Tub Leak In Previous Notes |
Troy Crews |
3/12/2020 |
Failed: Electrical - Permanent Power |
No Ground Wire On Service Entrance Box |
Matt Forsyth |
4/15/2020 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
4/17/2020 |
Release to power company |
|
Matt Forsyth |
4/17/2020 |
Passed: Building - Lath/Stucco |
Lath Inspection Not Required In Columbia County |
Tommy Matthews |
5/19/2020 |
Passed: Building - Final |
|
Matt Forsyth |
6/5/2020 |