Permit Details

Permit Search

Permit

New Residential Construction

809 NW MILO TER
LAKE CITY, FL 32055

Permit #
000038763
Application #
43830
Status Completed
  1. Submitted Oct 17, 2019
  2. Issued Oct 17, 2019
  3. Expires Dec 22, 2020
  4. Completed Jun 26, 2020

Property

Parcel #
02032-107
Owner
John & Elizabeth Harrison
Acres
5.01
Subdivision
Hills Of Huntsville
Zoning
A-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0280D
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
2628
Total Area (Sqft)
3721
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0652

Status & Review History

  1. Permit Issued

Contractors

  • Sara E Gresham

    John Norris Construction, Llc

    License
    CRC1331978
    Title
    Cert. Residential
    Role
    Contractor
  • Donald R Hollingsworth

    Holly Electric, Inc.

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Jan R Touchton

    Touchton's Heat & Air

    License
    CAC058747
    Title
    Cert. A/c Class “a”
    Role
    Subcontractor
  • Don C Bills Sr

    Hometown Plumbing Services Llc

    License
    CFC1428890
    Title
    Plumbing Contractor
    Role
    Subcontractor

Inspections

  1. Nov 5, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  2. Nov 13, 2019

    Passed: Building - Monolithic Slab

    Inspected by Matt Forsyth

  3. Nov 13, 2019

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  4. Dec 2, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  5. Dec 2, 2019

    Release to power company

    Inspected by Tommy Matthews

  6. Dec 27, 2019

    Building-

  7. Dec 27, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  8. Dec 27, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  9. Jan 10, 2020

    Passed: Building - Framing

    Inspected by Matt Forsyth

  10. Jan 10, 2020

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  11. Jan 10, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  12. Jan 16, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  13. Jan 23, 2020

    Passed: Building - Insulation

    Spray Foam Walls And Ceiling

    Inspected by Matt Forsyth

  14. Apr 28, 2020

    Septic Release Inspection

    Need Driveway Approval

    Inspected by Health Dept

  15. Apr 29, 2020

    Passed: Electrical - Permanent Power

    Need Driveway Release To Release Power

    Inspected by Matt Forsyth

  16. Jun 1, 2020

    Release to power company

    Inspected by Melissa Garber

  17. Jun 25, 2020

    Passed: Building - Final

    Release Of Co Pending Blower Door Test And Letter From Ac Contractor

    Inspected by Troy Crews

  18. Jun 26, 2020

    Certificate-Release Certificate

    Inspected by Troy Crews