Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
10/8/2019 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
10/8/2019 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
10/11/2019 |
Passed: Engineering - Setbacks |
|
Troy Crews |
10/11/2019 |
Passed: Electrical - Footer Steel & Grounding |
|
Troy Crews |
10/11/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
11/7/2019 |
Passed: Building - Roof Decking |
|
Troy Crews |
11/7/2019 |
Failed: Building - Framing |
Need Details On Porch Rafter Tie Downs, Need Details On Upstairs Inverted Hip Framing, Header Straps Missing Also Top Step On Stairs Over 8 Inches. |
Troy Crews |
12/20/2019 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
12/20/2019 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/20/2019 |
Failed: Mechanical - Rough In |
Nail Plates Missing For Refrigerant Lines Several Spots |
Troy Crews |
12/20/2019 |
Passed: Mechanical - Rough In |
Nail Plates Installed |
Troy Crews |
2/17/2020 |
Failed: Building - Framing |
Screws Need To Be Installed On Porch Rafters Per New Framing Details Call Back In With Insulation. |
Troy Crews |
2/17/2020 |
Passed: Building - Insulation |
|
Troy Crews |
3/4/2020 |
Passed: Electrical - Permanent Power |
Need Final Septic Release |
Troy Crews |
5/19/2020 |
Release to power company |
|
Lauire Hodson |
5/22/2020 |
Septic Release Inspection |
|
Health Dept |
5/22/2020 |
Failed: Building - Final |
Need Blower Door Test. Need Final Termite Spray. (both Rec'd 7-27-20) Gfi's Don't Work In Kitchen And Garage. Need Cleanout On Left Side Of House For Septic. |
Tommy Matthews |
7/23/2020 |
Passed: Building - Final |
|
Tommy Matthews |
7/28/2020 |