Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
1/9/2020 |
Failed: Building - Footer |
|
Matt Forsyth |
1/16/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
1/16/2020 |
Failed: Building - Monolithic Slab |
|
Matt Forsyth |
1/16/2020 |
Failed: Building - Slab |
Need Working Drawings |
Matt Forsyth |
1/16/2020 |
Passed: Building - Footer |
|
Matt Forsyth |
1/17/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
1/17/2020 |
Passed: Building - Monolithic Slab |
|
Matt Forsyth |
1/17/2020 |
Passed: Building - Slab |
|
Matt Forsyth |
1/17/2020 |
Failed: Building - Roof Decking |
To Many Exposed Nails(shiners)in Roof Need To Be Removed And Re Nailed |
Matt Forsyth |
3/17/2020 |
Failed: Building - Wall Sheathing |
Too Many Expose Nails In Wall Also Need Blocking At Edge Of 8 Foot Osb Nailed 6inches Oc |
Matt Forsyth |
3/17/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
3/19/2020 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
3/19/2020 |
Cancelled: Building - Framing |
|
Troy Crews |
6/8/2020 |
Cancelled: Electrical - 2nd Rough-In |
|
Troy Crews |
6/8/2020 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
6/8/2020 |
Cancelled: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
6/8/2020 |
Cancelled: Building - Framing |
|
Matt Forsyth |
7/9/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
7/9/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
7/9/2020 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
7/9/2020 |
Cancelled: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
7/9/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
7/24/2020 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
7/24/2020 |
Failed: Plumbing/Gas - Tub Set/Shower Pan |
Leak In Bathtub Piping |
Matt Forsyth |
7/24/2020 |
Passed: Building - Insulation |
|
Matt Forsyth |
9/24/2020 |
Failed: Plumbing/Gas - 2nd Rough-In |
Upstairs' Tub Not Holding Water |
Matt Forsyth |
9/24/2020 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
9/24/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
9/25/2020 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
9/25/2020 |
Septic Release Inspection |
|
Health Dept |
11/2/2020 |