Inspection |
Notes |
Performed By |
Date |
Failed: Plumbing/Gas - Underground Rough-In |
No Plans And Permit On Site. Could Not Verify Set Backs. |
Tommy Matthews |
8/21/2019 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
8/22/2019 |
Release to power company |
|
Troy Crews |
8/22/2019 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
8/22/2019 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
8/26/2019 |
Passed: Engineering - Setbacks |
|
Troy Crews |
8/26/2019 |
Failed: Building - Roof Decking |
Shiners Need To Be Removed And Replaced |
Tommy Matthews |
9/12/2019 |
Failed: Building - Ext Strapping/Wall Sheathing |
Shiners Need To Be Removed And Replaced. |
Tommy Matthews |
9/12/2019 |
Passed: Building - Roof Decking |
|
Tommy Matthews |
9/13/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
9/13/2019 |
Passed: Building - Framing |
|
Troy Crews |
9/27/2019 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
9/27/2019 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
9/27/2019 |
Passed: Mechanical - Above Ceiling |
|
Troy Crews |
9/27/2019 |
Passed: Mechanical - Rough In |
|
Troy Crews |
9/27/2019 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
9/27/2019 |
Passed: Building - Insulation |
|
Troy Crews |
10/3/2019 |
Failed: Electrical - Permanent Power |
Need Garage Door Installed To Protect Electrical Panel |
Matt Forsyth |
10/31/2019 |
Passed: Electrical - Permanent Power |
Need Health Release |
Troy Crews |
11/8/2019 |
Release to power company |
|
Mg |
11/21/2019 |
Septic Release Inspection |
|
Health Dept |
11/21/2019 |
Passed: Building - Final |
Release Pending Final Termite And Gfci On Washer Plug Items Received 12-4-19 |
Troy Crews |
11/26/2019 |