Permit Details

Permit Search

Permit

New Residential Construction

261 SW HIGHPOINT GLN
LAKE CITY, FL 32024

Permit #
000038489
Application #
42429
Status Completed
  1. Submitted Aug 19, 2019
  2. Issued Aug 19, 2019
  3. Expires Aug 11, 2020
  4. Completed Feb 18, 2020

Property

Parcel #
03406-113
Owner
Ronnie & Jocelyn Foxx
Acres
5.00
Subdivision
Rose Creek Plantation
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0383D
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2032.00
Total Area (Sqft)
2894.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0524

Status & Review History

No status updates yet.

Contractors

  • Bryan Zecher

    License
    CBC054575
    Title
    —
    Role
    —

Inspections

  1. Aug 22, 2019

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Aug 22, 2019

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Sep 10, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Sep 10, 2019

    Release to power company

    Inspected by Troy Crews

  5. Sep 10, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Sep 17, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  7. Sep 27, 2019

    Passed: Building - Lintel/Tie Beam

    Front Columns

    Inspected by Troy Crews

  8. Oct 8, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  9. Oct 11, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. Oct 15, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  11. Oct 31, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  12. Oct 31, 2019

    Passed: Mechanical - Above Ceiling

    Inspected by Troy Crews

  13. Oct 31, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Oct 31, 2019

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  15. Oct 31, 2019

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  16. Nov 12, 2019

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  17. Jan 9, 2020

    Passed: Electrical - Permanent Power

    Need Septic, drive Rec'd 1/14/20

    Inspected by Troy Crews

  18. Jan 17, 2020

    Release to power company

    Inspected by Mg

  19. Jan 17, 2020

    Septic Release Inspection

    Inspected by Health Dept

  20. Jan 21, 2020

    Release to power company

    Eh Rec'd. 01.21.20

    Inspected by Tc

  21. Feb 13, 2020

    Passed: Building - Final

    Inspected by Troy Crews