Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Tommy Matthews |
8/13/2019 |
Passed: Engineering - Setbacks |
|
Tommy Matthews |
8/13/2019 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
8/20/2019 |
Release to power company |
|
Matt Forsyth |
8/20/2019 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Matt Forsyth |
8/20/2019 |
Passed: Building - Slab |
|
Tommy Matthews |
8/26/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
10/4/2019 |
Passed: Building - Roof Decking |
|
Troy Crews |
10/4/2019 |
Passed: Electrical - 2nd Rough-In |
|
Tommy Matthews |
10/21/2019 |
Passed: Mechanical - Rough In |
|
Tommy Matthews |
10/21/2019 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Tommy Matthews |
10/21/2019 |
Failed: Building - Framing |
All Threads Do Not Match That Shown On Shearwall Layout Sheet A-8 Of Design Drawings Especially Missing On Interior Load Bearing Wall.
needs Minimum 2 King Studs At Every Opening.
9’ Openings Missing King Studs.
need Anchor Bolts Each Side Of Break In Base Plate.
trusses Do Not Match With Truss Plans Sealed With Review Seal. |
Tommy Matthews |
10/21/2019 |
Failed: Plumbing/Gas - Tub Set/Shower Pan |
Not Required In Columbia County. |
Tommy Matthews |
10/21/2019 |
Failed: Building - Framing |
Need Option From Engineer On Missing All Thread Interior Bearing Wall. |
Troy Crews |
10/23/2019 |
Passed: Building - Framing |
Engineer Letter Provided For Interior Bearing Wall |
Troy Crews |
10/24/2019 |
Passed: Building - Insulation |
|
Troy Crews |
10/25/2019 |
Failed: Electrical - Permanent Power |
Need Septic Release, And Lockable Doors Exterior. |
Troy Crews |
12/12/2019 |
Septic Release Inspection |
|
Health Dept |
12/16/2019 |
Passed: Electrical - Permanent Power |
Locks Installed |
Troy Crews |
12/16/2019 |
Release to power company |
|
Troy Crews |
12/16/2019 |
Passed: Building - Final |
|
Matt Forsyth |
1/27/2020 |