Status Completed
  1. Submitted Aug 2, 2019
  2. Issued Aug 2, 2019
  3. Expires May 6, 2020
  4. Completed Nov 8, 2019

Property

Parcel #
02284-102
Owner
Concept Development Inc
Acres
5.00
Subdivision
Crs Bascom Norris At Lake Jeffery
Zoning
CI
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0283D
This is the construction of a:
DOLLAR GENERAL STORE
Driveway access to property:
Culvert Waiver
Is there a Fire Sprinkler System?
No
Setbacks Front
20.00
Setback Side 1
15.00
Setback Side 2
15.00
Setback Rear
5.00
Stories
1
Heated Area (Sqft)
9100.00
Total Area (Sqft)
9100.00
Building Height
19
Building Code Construction Type
II
Building Code Element
B
Building Code Occupancy Types
Mercantile
Occupancy Use Title
Retail Store
Dev Permit #
F023-
Design Occupant Load
137
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X-CITY

Status & Review History

No status updates yet.

Contractors

  • Brian Scott Crawford

    License
    CGC1515491
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Aug 14, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  2. Aug 14, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  3. Aug 19, 2019

    Failed: Building - Footer

    Covered In Water

    Inspected by Troy Crews

  4. Aug 19, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Aug 21, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  6. Aug 21, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  7. Aug 21, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  8. Aug 21, 2019

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Troy Crews

  9. Sep 5, 2019

    Passed: Building - Vertical Cells/Columns

    Inspected by Troy Crews

  10. Sep 5, 2019

    Passed: Building - Lintel/Tie Beam

    Inspected by Troy Crews

  11. Sep 27, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Sep 27, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  13. Sep 27, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Sep 27, 2019

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  15. Oct 3, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  16. Oct 3, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  17. Oct 9, 2019

    Cancelled: Engineering - Final Driveway

    8/2/19 David Mccormick Failed. Need To Purchase A Culvert Permit And Install.

    Inspected by Laurie Hodson

  18. Oct 10, 2019

    Failed: Electrical - Permanent Power

    Need Building Secured Door Locks, Completion Of Front Entry Glass, Wire Nut All Open Conductors

    Inspected by Troy Crews

  19. Oct 14, 2019

    Passed: Electrical - Permanent Power

    Need Elevation Letter For Release

    Inspected by Troy Crews

  20. Oct 16, 2019

    Failed: Building - Lintel/Tie Beam

    No Further Inspections Until Stamped Letter Received On Elevation. Note No Inspections This Area In Afternoon.

    Inspected by Troy Crews

  21. Oct 17, 2019

    Passed: Building - Lintel/Tie Beam

    Dumpster Enclosure

    Inspected by Troy Crews

  22. Oct 17, 2019

    Passed: Building - Masonry Wall Reinforcing

    Inspected by Troy Crews

  23. Oct 22, 2019

    Release to power company

  24. Oct 30, 2019

    Passed: Electrical - Permanent Power

    Final In Building

    Inspected by Troy Crews

  25. Oct 30, 2019

    Passed: Mechanical - Performance Test and Balance

    Inspected by Troy Crews

  26. Oct 30, 2019

    Passed: Plumbing/Gas - Sanitary

    Inspected by Troy Crews

  27. Nov 1, 2019

    Passed: Building - Final

    Release Pending Fire Final, And Zoning Final

    Inspected by Troy Crews

  28. Nov 6, 2019

    Passed: Engineering - Zoning Final

    Initial Inspection Failed Due To Two Missing Oak Trees And Fire Hydrant Not In Approved Location. Applicant Applied For A Minor Modification To An Approved Site Plan For The Relocation Of The Fire Hydrant. Fire Department Approved New Location On November 6, 2019. Two Missing Oak Trees Have Been Planted. Engineer Final Complete

    Inspected by Brandon Stubbs

  29. Nov 7, 2019

    Passed: Fire - Fire Final

    Per Tad - He Does Need To Measure Shelving-lh 11/7/19

    Inspected by Tad Cervantes

  30. Nov 8, 2019

    Passed: Fire - Fire Final

    Shelving Egress

    Inspected by Tad Cervantes