Inspection |
Notes |
Performed By |
Date |
Release to power company |
Corrected Power Company |
Tc |
8/26/2019 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
8/26/2019 |
Release to power company |
|
Troy Crews |
8/26/2019 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
9/5/2019 |
Passed: Building - Slab |
|
Troy Crews |
9/11/2019 |
Passed: Electrical - Footer Steel & Grounding |
|
Troy Crews |
9/11/2019 |
Passed: Electrical - 2nd Rough-In |
Rough In Office Areas |
Troy Crews |
11/8/2019 |
Passed: Building - Framing |
Office Area Ok,call Back In For Firewall Between Layers Of Rock |
Troy Crews |
11/12/2019 |
Failed: Mechanical - Above Ceiling |
Not Complete Call Back In With Insulation |
Troy Crews |
11/15/2019 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
11/15/2019 |
Septic Release Inspection |
|
Health Dept |
11/27/2019 |
Passed: Mechanical - Rough In |
|
Troy Crews |
12/4/2019 |
Failed: Electrical - Permanent Power |
Need Elevation Confirmation Letter From Surveyor, Rec'd Elev Ltr |
Troy Crews |
12/4/2019 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
12/6/2019 |
Release to power company |
|
Troy Crews |
12/6/2019 |
Failed: Building - Final |
Need Gfci Receptacle Near Service Sink, Thresholds In Interior Exceed 1/2 Inch For Accessibility.accessible. Parking And Striping Not Complete. East Side Lease Space Toilet Exceeds 18 Inch Maximum From Wall. |
Troy Crews |
12/13/2019 |
Failed: Engineering - Zoning Final |
Site Not Constructed In Accordance With Approved Site & Development Plan. |
Brandon Stubbs |
12/16/2019 |
Passed: Fire - Aboveground Hydro - Sprinkler |
|
Tad Cervantes |
12/17/2019 |
Passed: Fire - Aboveground Sprinkler - Visual (On Site) |
|
Tad Cervantes |
12/17/2019 |
Passed: Fire - Fire Final |
|
Tad Cervantes |
12/17/2019 |
Passed: Fire - Fire Final |
|
Tad Cervantes |
12/17/2019 |
Passed: Engineering - Zoning Final |
|
Brandon Stubbs |
4/30/2020 |
Passed: Building - Final |
|
Troy Crews |
5/4/2020 |