Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 377 SW EMORYWOOD GLN
LAKE CITY, FL 32024
Parcel #: 03397-204
Acres: 1.67
Owner: Nicholas Rimert
Subdivision: Cove At Rose Creek 1/3 Part Of
Zoning: AG-3
Flood Zone: X
District: 5
Application #: 42275
Permit #: 000038398
Related Permit: Culvert: 000002848
Submitted: Tuesday, July 23, 2019
Issued: Tuesday, July 23, 2019
Expires: Monday, May 18, 2020
Completed: Monday, May 18, 2020
Status: Completed
Septic Release? Yes
Notes:
PER PLAT MINIMUM FLOOR ELEVATION IS 83.9', NEED ELEVATION CONFIRMATION LETTER AT SLAB, LOT SPLIT THROUGH PRIOR FAMILY LOT 14.9 IN 2009. ELEVATION LETTER REC'D AT 89.49'.
Job Details
This is the construction of a SFD, UTILITY
Heated Area (Sqft) 2152.00
Total Area (Sqft) 3121.00
Stories 1
Setbacks Front 30.00
Setback Side 1 25.00
Setback Side 2 25.00
Setbacks Rear 25.00
Septic# (00-0000) or (X00-000) 19-0459
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0383D
Review Notes
Contractors
Name/ Business License Title Role
Isaiah Cully

CBC1259655
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Mccormick, David 7/26/2019
Passed: Building - Footer Tommy Matthews 8/12/2019
Passed: Engineering - Setbacks Tommy Matthews 8/12/2019
Passed: Electrical - Temporary Service Tommy Matthews 8/23/2019
Release to power company Tommy Matthews 8/23/2019
Passed: Plumbing/Gas - Underground Rough-In Tommy Matthews 8/23/2019
Failed: Building - Slab No Plastic Installed Troy Crews 8/26/2019
Passed: Electrical - Temporary Service Tommy Matthews 8/30/2019
Release to power company Tommy Matthews 8/30/2019
Passed: Building - Slab Pending Design Of Interior Footing. Need Elevation Of Slab After Slab Is Poured. Tommy Matthews 8/30/2019
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 11/8/2019
Failed: Building - Framing Anchor Bolts Some Missing, Also Some Missing Washers. Need Framing Details From Architect For Front Porch Framing, Check Truss Bracing And Strapping Some Missing. Also Nail Off Buckets For Porch Post Bottom. Call Back In With Rough In Inspections. Troy Crews 11/8/2019
Failed: Building - Framing Garage Tie Downs Not Done Troy Crews 11/25/2019
Failed: Mechanical - Rough In Bath Fans Not Ducte Troy Crews 11/25/2019
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 11/25/2019
Passed: Electrical - 2nd Rough-In Troy Crews 11/25/2019
Passed: Building - Framing Troy Crews 12/6/2019
Passed: Mechanical - Rough In Troy Crews 12/6/2019
Passed: Building - Insulation Troy Crews 1/30/2020
Septic Release Inspection Need Elevation Letter Health Dept 4/14/2020
Passed: Engineering - Final Driveway Mccormick, David 5/4/2020
Failed: Electrical - Permanent Power Garage Needs To Be Lockable Because Electrical Panel Is Located In Garage. Need Elevation Certificate. Tommy Matthews 5/6/2020
Failed: Electrical - Permanent Power Need Elevation Letter, Rec'd 5.11.20 Troy Crews 5/11/2020
Passed: Electrical - Permanent Power Tommy Matthews 5/12/2020
Release to power company Tommy Matthews 5/12/2020
Passed: Building - Final Matt Forsyth 5/18/2020