Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 362 SW MAYFAIR LN
LAKE CITY, FL 32024
Parcel #: 02911-350
Acres: 0.66
Owner: Trent Giebeig Construction Inc
Subdivision: Mayfair
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 42128
Permit #: 000038315
Related Permit: Culvert Waiver: 000002838
Submitted: Wednesday, July 3, 2019
Issued: Wednesday, July 3, 2019
Expires: Monday, January 13, 2020
Completed: Monday, January 13, 2020
Status: Completed
Septic Release? Yes
Notes:
MINIMUM FLOOR ELEVATION PER PLAT 150.0', NEED ELEVATION LETTER AT SLAB, STRING FRONT PROPERTY LINE FOR INSPECTION, NOC REC'D, ELEVATION LETTER REC'D AT 150.26'
Job Details
Finished floor requirement
Fema map number 12023C0290D
This is the construction of a SFD, UTILITY
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Stories 1
Heated Area (Sqft) 1600.00
Total Area (Sqft) 2283.00
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000) 18-0519
Review Notes
Contractors
Name/ Business License Title Role
Trent Giebeig

CRC1330693
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Need Potti Before Next Inspection Tommy Matthews 9/9/2019
Passed: Engineering - Setbacks Tommy Matthews 9/9/2019
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 9/18/2019
Passed: Building - Slab Matt Forsyth 9/20/2019
Failed: Electrical - Temporary Service Need Holes In Panel Box To Be Sealed. Tommy Matthews 9/25/2019
Passed: Electrical - Temporary Service Matt Forsyth 10/3/2019
Release to power company Matt Forsyth 10/3/2019
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 11/1/2019
Failed: Building - Framing Engineering In Attic Will Be Done On The Inspection Of The Insulation Matt Forsyth 11/21/2019
Passed: Electrical - 2nd Rough-In Matt Forsyth 11/21/2019
Passed: Mechanical - Rough In Matt Forsyth 11/21/2019
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 11/21/2019
Passed: Building - Framing Matt Forsyth 11/25/2019
Passed: Building - Insulation Insulation Inspection For Walls Only Matt Forsyth 11/25/2019
Passed: Electrical - Permanent Power Need Septic Release Matt Forsyth 12/26/2019
Septic Release Inspection Health Dept 12/26/2019
Release to power company Mg 12/27/2019
Failed: Building - Final Need Elevation Letter need Blower Door Test Results Tommy Matthews 1/8/2020
Passed: Building - Final All Needed Doc's Rec'd 1.13.20 Tommy Matthews 1/13/2020