Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
7/5/2019 |
Passed: Building - Footer |
Need Engineer Letter Before Slab |
Troy Crews |
7/5/2019 |
Passed: Engineering - Setbacks |
|
Troy Crews |
7/5/2019 |
Failed: Electrical - Temporary Service |
Connect Ground Wire And Secure Panels And Mast To Pole |
Troy Crews |
7/15/2019 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
7/15/2019 |
Passed: Building - Slab |
|
Troy Crews |
7/18/2019 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
7/18/2019 |
Release to power company |
|
Troy Crews |
7/18/2019 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
8/16/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
8/16/2019 |
Passed: Building - Framing |
|
Matt Forsyth |
8/16/2019 |
Passed: Electrical - Rough In |
|
Tommy Matthews |
8/30/2019 |
Passed: Mechanical - Rough In |
|
Tommy Matthews |
8/30/2019 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Tommy Matthews |
8/30/2019 |
Passed: Plumbing/Gas - Rough In |
Need Pressure On Supply Lines. |
Tommy Matthews |
8/30/2019 |
Passed: Building - Insulation |
Attic Will Be Blown In Insulation |
Matt Forsyth |
9/5/2019 |
Passed: Electrical - Permanent Power |
|
Tommy Matthews |
10/30/2019 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
11/21/2019 |
Passed: Electrical - Permanent Power |
Need Follow Up Letter From Engineer Regarding Site Work, Health Release--rec'd, Driveway Release. |
Troy Crews |
11/21/2019 |
Septic Release Inspection |
|
Health Dept |
11/21/2019 |
Release to power company |
|
Mg |
11/22/2019 |
Passed: Building - Final |
|
Troy Crews |
12/23/2019 |