Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 261 SW DEANNA TERR
LAKE CITY, FL 32025
Parcel #: 08111-105
Acres: 0.82
Owner: Chad Aaron & Holly Boris Brinkley
Subdivision: Holly Hill
Zoning: RSF-2
Flood Zone: X
District: 5
Application #: 42127
Permit #: 000038313
Related Permit: Culvert: 000002837
Submitted: Wednesday, July 3, 2019
Issued: Wednesday, July 3, 2019
Expires: Thursday, December 26, 2019
Completed: Thursday, December 26, 2019
Status: Completed
Septic Release? Yes
Notes:
FLOOR ONE FOOT ABOVE THE ROAD, PROJECT SITE REVIEWED WITH CONTRACTOR AND PUBLIC WORKS DEPT-SITE INSPECTION AND DOCUMENTS FOLLOW UP REQUIRED, NOC REC'D FOLLOW UP LETTER FROM ENGINEER IN FILE ON SITE WORK.
Job Details
This is the construction of a SFD, UTILITY
Heated Area (Sqft) 1976.00
Total Area (Sqft) 3111.00
Stories 1
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Septic# 18-0929
Power Company CLAY
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0292D
Review Notes
Contractors
Name/ Business License Title Role
Trent Giebeig

CRC1330693
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Mccormick, David 7/5/2019
Passed: Building - Footer Need Engineer Letter Before Slab Troy Crews 7/5/2019
Passed: Engineering - Setbacks Troy Crews 7/5/2019
Failed: Electrical - Temporary Service Connect Ground Wire And Secure Panels And Mast To Pole Troy Crews 7/15/2019
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 7/15/2019
Passed: Building - Slab Troy Crews 7/18/2019
Passed: Electrical - Temporary Service Troy Crews 7/18/2019
Release to power company Troy Crews 7/18/2019
Passed: Building - Roof Decking Matt Forsyth 8/16/2019
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 8/16/2019
Passed: Building - Framing Matt Forsyth 8/16/2019
Passed: Electrical - Rough In Tommy Matthews 8/30/2019
Passed: Mechanical - Rough In Tommy Matthews 8/30/2019
Passed: Plumbing/Gas - Tub Set/Shower Pan Tommy Matthews 8/30/2019
Passed: Plumbing/Gas - Rough In Need Pressure On Supply Lines. Tommy Matthews 8/30/2019
Passed: Building - Insulation Attic Will Be Blown In Insulation Matt Forsyth 9/5/2019
Passed: Electrical - Permanent Power Tommy Matthews 10/30/2019
Passed: Engineering - Final Driveway Mccormick, David 11/21/2019
Passed: Electrical - Permanent Power Need Follow Up Letter From Engineer Regarding Site Work, Health Release--rec'd, Driveway Release. Troy Crews 11/21/2019
Septic Release Inspection Health Dept 11/21/2019
Release to power company Mg 11/22/2019
Passed: Building - Final Troy Crews 12/23/2019
Documents