Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 275 SW BEACON WAY
LAKE CITY, FL 32025
Parcel #: 02951-115
Acres: 0.73
Owner: Danny Statter
Subdivision: Amelia Landing
Zoning: PRD
Flood Zone: X
District: 5
Application #: 40962
Permit #: 000038188
Related Permit:
Submitted: Tuesday, June 4, 2019
Issued: Monday, May 11, 2020
Expires: Friday, December 4, 2020
Completed: Friday, December 4, 2020
Status: Completed
Septic Release? Yes
Notes:
MFE @ 117.00'. ELEVATION CONFIRMATION LETTER @ SLAB. NOC REC'D. ELEVATION LETTER REC'D AT 117.28'
Job Details
This is the construction of a SFD/UTILITY
Heated Area (Sqft) 1610.00
Total Area (Sqft) 2201.00
Stories 1
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Septic# X-CITY
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0293D
Review Notes
5/11/2020 Permit Renewed Permit renewed. Original approved date of 6/4/2019 expired on 12/2/2019
Contractors
Name/ Business License Title Role
Bradley Franks

R291103874
Inspections
Inspection Notes Performed By Date
Failed: Building - Footer No Plans On Project Matt Forsyth 6/5/2019
Passed: Engineering - Setbacks Matt Forsyth 6/5/2019
Passed: Building - Footer Matt Forsyth 5/12/2020
Passed: Engineering - Setbacks Matt Forsyth 5/12/2020
Passed: Plumbing/Gas - 1st Underground Rough–In Tommy Matthews 5/19/2020
Failed: Building - Slab Porches Require Wire Chairs As Per Plans. Tommy Matthews 5/21/2020
Passed: Building - Slab Tommy Matthews 5/26/2020
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 6/8/2020
Passed: Building - Roof Decking Tommy Matthews 6/16/2020
Passed: Building - Framing Matt Forsyth 6/23/2020
Passed: Electrical - Temporary Service Matt Forsyth 6/23/2020
Release to power company Matt Forsyth 6/23/2020
Passed: Electrical - 2nd Rough-In Matt Forsyth 7/9/2020
Passed: Mechanical - Rough In Matt Forsyth 7/9/2020
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 7/9/2020
Passed: Building - Insulation Walls Only Matt Forsyth 7/10/2020
Passed: Electrical - Permanent Power Troy Crews 9/22/2020
Release to power company Troy Crews 9/22/2020
Failed: Building - Final Need Drain Pan Under Air Handler, Seal Pan Drain Line For Water Heater, Need Blower Door Test. Troy Crews 11/25/2020
Failed: Building - Final House Locked No Code Troy Crews 12/3/2020
Passed: Building - Final Release Pending Blower Door Test Troy Crews 12/3/2020
Certificate-Release Certificate Blower Door Test Received Troy Crews 12/4/2020