Permit Details

Permit Search

Permit

New Residential Construction

324 SW JORDAN ST
FT. WHITE, FL 32038

Permit #
000038036
Application #
40738
Status Completed
  1. Submitted Apr 26, 2019
  2. Issued Apr 26, 2019
  3. Expires May 24, 2020
  4. Completed Dec 2, 2019

Property

Parcel #
14309-003
Owner
Erroll & Gloria Jackson
Acres
0.50
Subdivision
Unrec Survey - Parcek
Zoning
FT. WHITE
Flood zone
FW
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0490C
This is the construction of a
SFD/UTILITY
Heated Area (Sqft)
2071.00
Total Area (Sqft)
2395.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0615

Status & Review History

No status updates yet.

Contractors

  • Bryan Zecher

    License
    CBC1257343
    Title
    —
    Role
    —

Inspections

  1. Jun 4, 2019

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Jun 4, 2019

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Jun 7, 2019

    Passed: Electrical - Temporary Service

    Close Holes In Bottom Of Panel Box. Will Check On Next Inspection.

    Inspected by Tommy Matthews

  4. Jun 7, 2019

    Release to power company

    Inspected by Tommy Matthews

  5. Jun 25, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Tommy Matthews

  6. Jul 2, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  7. Jul 29, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  8. Jul 29, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  9. Jul 29, 2019

    Passed: Building - Framing

    Inspected by Matt Forsyth

  10. Aug 19, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  11. Aug 19, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Aug 19, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  13. Aug 23, 2019

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  14. Oct 16, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  15. Oct 17, 2019

    Release to power company

    Inspected by Lh

  16. Oct 17, 2019

    Septic Release Inspection

    Inspected by Health Dept

  17. Nov 26, 2019

    Passed: Building - Final

    Inspected by Tommy Matthews