Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 449 SW MADISON CT
LAKE CITY, FL 32024
Parcel #: 02791-106
Acres: 5.01
Owner: Sharon Baldauf-madero & Mark Madero
Subdivision: Westwind Estates
Zoning: A-3
Flood Zone: X
District: 2
Application #: 40541
Permit #: 000037899
Related Permit:
Submitted: Monday, March 25, 2019
Issued: Monday, March 25, 2019
Expires: Monday, November 16, 2020
Completed: Monday, November 16, 2020
Status: Completed
Septic Release? Yes
Notes:
ONE FOOT ABOVE ROAD. NOC ON FILE, ENGINEER LETTER REC'D WITH REQUIREMENTS- STRUCTURE SHALL BE 12 INCHES ABOVE THE EXISTING GROUND AT ANY POINT ALONG THE PERIMETER AND IN NO CASE SHALL THE FINISHED FLOOR ELEVATION BE LESS THAN 111.00', NEED ELEVATION LETTER FROM SURVEYOR AT 111.00 OR ABOVE. SURVEYOR ELEVATION LETTER REC'D - FINISHED FLOOR ELEVATION IS 114.7'.
Job Details
Finished floor requirement
Fema map number 12023C0290D
This is the construction of a SFD/UTILITY
Setbacks Front 30.00
Setback Side 1 25.00
Setback Side 2 25.00
Setbacks Rear 25.00
Heated Area (Sqft) 2532.00
Total Area (Sqft) 3780.00
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000) 19-0170
Review Notes
Contractors
Name/ Business License Title Role
Sharon B-madero & Mark Madero

OWNER
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Troy Crews 4/2/2019
Passed: Engineering - Setbacks Troy Crews 4/2/2019
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 5/10/2019
Passed: Building - Slab Troy Crews 5/14/2019
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 10/8/2019
Passed: Building - Framing Troy Crews 10/30/2019
Passed: Building - Roof Decking Troy Crews 10/30/2019
Passed: Electrical - 2nd Rough-In Troy Crews 2/11/2020
Passed: Mechanical - Rough In Troy Crews 4/30/2020
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 4/30/2020
Passed: Building - Insulation Troy Crews 6/10/2020
Septic Release Inspection Health Dept 9/9/2020
Passed: Electrical - Permanent Power Troy Crews 9/22/2020
Release to power company Troy Crews 9/22/2020
Passed: Building - Final Troy Crews 11/16/2020