Permit Details

Permit Search

Permit

New Residential Construction

237 SW PADDOCK CT
LAKE CITY, FL 32025

Permit #
000037859
Application #
40472
Status Completed
  1. Submitted Mar 13, 2019
  2. Issued Mar 13, 2019
  3. Expires Apr 1, 2020
  4. Completed Oct 4, 2019

Property

Parcel #
08920-108
Owner
Mf Butler Homes Llc
Acres
2.14
Subdivision
Briarwood
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0382D
This is the construction of a
SFD, UTILITY
Stories
1
Heated Area (Sqft)
2245.00
Total Area (Sqft)
3209.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0169

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    License
    CBC1259633
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Mar 14, 2019

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  2. Mar 14, 2019

    Failed: Building - Footer

    Need Evaluation On Clay

    Inspected by Tommy Matthews

  3. Apr 9, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  4. Apr 9, 2019

    Release to power company

    Inspected by Tommy Matthews

  5. Apr 16, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Apr 18, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  7. May 20, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. May 20, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. May 31, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  10. May 31, 2019

    Failed: Electrical - Rough In

    Need Island Power Kitchen Call Back In With Insulation

    Inspected by Troy Crews

  11. May 31, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. May 31, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  13. Jun 7, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Jul 12, 2019

    Septic Release Inspection

    Inspected by Health Dept

  15. Jul 17, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  16. Jul 17, 2019

    Release to power company

    Inspected by Tommy Matthews

  17. Oct 4, 2019

    Passed: Building - Final

    Need Picture Of Fresh Air Line For Release, Rec'd

    Inspected by Troy Crews