Permit Details

Permit Search

Permit

New Residential Construction

180 SW ETHEL GLN
LAKE CITY, FL 32024

Permit #
000037838
Application #
40431
Status Completed
  1. Submitted Mar 7, 2019
  2. Issued Mar 7, 2019
  3. Expires Mar 17, 2020
  4. Completed Sep 19, 2019

Property

Parcel #
02739-227
Owner
John Norris, Ii.
Acres
0.61
Subdivision
Turkey Run
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Heated Area (Sqft)
1750.00
Total Area (Sqft)
2569.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0530

Status & Review History

No status updates yet.

Contractors

  • Sara Gresham

    License
    CRC1331978
    Title
    —
    Role
    —

Inspections

  1. Mar 13, 2019

    Release to power company

    Inspected by Troy Crews

  2. Mar 13, 2019

    Release to power company

    Corrected Power Company

    Inspected by Laurie Hodson

  3. Mar 13, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Mar 22, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Watch For One Foot Requirement Above Road

    Inspected by Tommy Matthews

  5. Mar 29, 2019

    Passed: Building - Slab

    Elevation Letter From Engineer Pending.

    Inspected by Troy Crews

  6. Mar 29, 2019

    Failed: Building - Slab

    Awaiting Engineer Letter On Slab Height

    Inspected by Troy Crews

  7. Apr 1, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  8. Apr 1, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  9. May 31, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Walls Only

    Inspected by Troy Crews

  10. Jun 4, 2019

    Passed: Building - Roof Decking

    Call Back In For Back Porch

    Inspected by Troy Crews

  11. Jun 11, 2019

    Passed: Building - Roof Decking

    Back Porch

    Inspected by Troy Crews

  12. Jun 27, 2019

    Failed: Building - Framing

    T01 -g Truss Straps, T-o6 Truss Straps, Check All King Studs Add Per Plan, Call Back In Prior To Insulation

    Inspected by Troy Crews

  13. Jun 27, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  14. Jun 27, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Jun 27, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  16. Jul 2, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  17. Jul 23, 2019

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  18. Aug 26, 2019

    Septic Release Inspection

    Inspected by Health Dept

  19. Sep 9, 2019

    Passed: Electrical - Permanent Power

    Culvert On Separate Permit

    Inspected by Troy Crews

  20. Sep 9, 2019

    Release to power company

    Inspected by Troy Crews

  21. Sep 19, 2019

    Passed: Building - Final

    Inspected by Troy Crews