Status Completed
  1. Submitted Mar 5, 2019
  2. Issued Mar 5, 2019
  3. Expires Jan 22, 2020
  4. Completed Jul 31, 2019

Property

Parcel #
09280-119
Owner
Isaac Hart
Acres
2.00
Subdivision
Oaks Of Lake City
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0395C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2803
Total Area (Sqft)
3836
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0166

Status & Review History

No status updates yet.

Contractors

  • Isaiah Cully

    License
    CBC1259655
    Title
    —
    Role
    —

Inspections

  1. Mar 6, 2019

    Release to power company

    Inspected by Troy Crews

  2. Mar 7, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  3. Mar 7, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  4. Mar 7, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  5. Mar 19, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Mar 21, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Apr 9, 2019

    Passed: Building - Roof Decking

    Partial Call Back In For Other Half

    Inspected by Troy Crews

  8. Apr 9, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. May 7, 2019

    Failed: Building - Framing

    T-04 Truss Strapping And Girder Strap At Bottom, Garage Header Details And Tie Downs Not Per Plan, Tie Downs At End Of Each Shearwall?are They Needed Question For Architect.

    Inspected by Troy Crews

  10. May 7, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  11. May 13, 2019

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  12. May 13, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  13. May 13, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. May 21, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. Jun 19, 2019

    Septic Release Inspection

    Inspected by Health Dept

  16. Jun 24, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  17. Jun 24, 2019

    Release to power company

    Inspected by Tommy Matthews

  18. Jul 8, 2019

    Passed: Building - Final

    Need Final Termite Treatment-rec'd 7/12/19. One Outlet In Laundry Room Needs To Be Gfci.

    Inspected by Tommy Matthews

  19. Jul 26, 2019

    Passed: Building - Final

    Inspected by Tommy Matthews