Permit Details

Permit Search

Permit

New Residential Construction

733 SW MARYNIK DR
HIGH SPRINGS, FL 32643

Permit #
000037778
Application #
40362
Status Completed
  1. Submitted Feb 21, 2019
  2. Issued Feb 21, 2019
  3. Expires Mar 2, 2020
  4. Completed Sep 4, 2019

Property

Parcel #
10006-237
Owner
Rodney & Nancy Denham
Acres
5.10
Subdivision
River Rise
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0513C
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2034.00
Total Area (Sqft)
3007.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0122

Status & Review History

No status updates yet.

Contractors

This is an owner-builder project.

  • Rodney & Nancy Denham

    License
    OWNERS
    Title
    —
    Role
    —

Inspections

  1. Mar 5, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  2. Mar 6, 2019

    Release to power company

  3. Mar 11, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Mar 13, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  5. Mar 13, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Apr 11, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Apr 11, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Apr 11, 2019

    Cancelled: Building - Framing

    Inspected by Troy Crews

  9. Apr 17, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  10. Apr 17, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  11. Apr 17, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  12. Apr 26, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  13. Apr 26, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. May 2, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. May 22, 2019

    Septic Release Inspection

    Inspected by Health Dept

  16. Jul 9, 2019

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Jul 9, 2019

    Release to power company

    Inspected by Troy Crews

  18. Aug 5, 2019

    Passed: Building - Final

    Release Pending Blower Door Test

    Inspected by Troy Crews

  19. Sep 4, 2019

    Passed: Building - Final

    Blower Door Test Received

    Inspected by Troy Crews