Permit Details

Permit Search

Permit

New Residential Construction

4408 SE HIGH FALLS RD
LAKE CITY, FL 32025

Permit #
000037660
Application #
40179
Status Completed
  1. Submitted Jan 22, 2019
  2. Issued Jan 22, 2019
  3. Expires Jan 26, 2020
  4. Completed Jul 31, 2019

Property

Parcel #
09216-010
Owner
Adam Holloway
Acres
9.85
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0405C
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Heated Area (Sqft)
1876.00
Total Area (Sqft)
2824.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0045

Status & Review History

No status updates yet.

Contractors

  • Douglas Edgley

    License
    CRC1330689
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Jan 23, 2019

    Septic Release Inspection

    Inspected by Health Dept

  2. Feb 12, 2019

    Passed: Building - Footer

    Inspected by Tommy Matthews

  3. Feb 12, 2019

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  4. Feb 20, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Tommy Matthews

  5. Feb 22, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  6. Mar 5, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  7. Mar 12, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Mar 28, 2019

    Failed: Building - Framing

    Check Uplift On Trusses washers On Anchor Bolts Need 3” Washers check Jacks And Kings At Headers check All Requirements Of Framing, Etc.

    Inspected by Tommy Matthews

  9. Mar 28, 2019

    Passed: Electrical - Rough In

    Inspected by Tommy Matthews

  10. Mar 28, 2019

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  11. Mar 28, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Tommy Matthews

  12. Mar 29, 2019

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  13. Apr 3, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Jun 27, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  15. Jun 27, 2019

    Release to power company

    Inspected by Tommy Matthews

  16. Jul 30, 2019

    Passed: Building - Final

    Inspected by Troy Crews