Permit Details

Permit Search

Permit

New Residential Construction

116 SW LUCILE CT
LAKE CITY, FL 32025

Permit #
000037623
Application #
40122
Status Completed
  1. Submitted Jan 14, 2019
  2. Issued Jan 14, 2019
  3. Expires Oct 22, 2019
  4. Completed Apr 26, 2019

Property

Parcel #
02911-331
Owner
Trent Giebeig Construction,inc.
Acres
0.51
Subdivision
May-fair
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1600.00
Total Area (Sqft)
2186.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0237

Status & Review History

No status updates yet.

Contractors

  • B. Trent Giebeig

    License
    CRC1330693
    Title
    —
    Role
    —

Inspections

  1. Jan 28, 2019

    Cancelled: Building - Footer

    Inspected by Troy Crews

  2. Jan 28, 2019

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jan 28, 2019

    Failed: Electrical - Temporary Service

    Outlets Need G.f.c.i Protection

    Inspected by Troy Crews

  4. Jan 31, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  5. Jan 31, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Jan 31, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  7. Feb 7, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  8. Feb 11, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  9. Feb 18, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  10. Feb 18, 2019

    Release to power company

    Inspected by Troy Crews

  11. Mar 8, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  12. Mar 15, 2019

    Failed: Building - Framing

    Min. 2 Studs Under Girder Truss (1 Place) check All All-treads. Some Loose

    Inspected by Tommy Matthews

  13. Mar 25, 2019

    Passed: Building - Framing

    Inspected by Tommy Matthews

  14. Mar 25, 2019

    Passed: Electrical - Rough In

    Inspected by Tommy Matthews

  15. Mar 25, 2019

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  16. Mar 25, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Tommy Matthews

  17. Mar 28, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  18. Mar 28, 2019

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  19. Apr 12, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  20. Apr 12, 2019

    Cancelled: Electrical - Permanent Power

    Inspected by Troy Crews

  21. Apr 12, 2019

    Cancelled: Electrical - Permanent Power

    Inspected by Troy Crews

  22. Apr 15, 2019

    Release to power company

    Eh Health Number Was Wrong On Permit.

    Inspected by Tc/jlw

  23. Apr 15, 2019

    Septic Release Inspection

    Inspected by Health Dept

  24. Apr 25, 2019

    Passed: Building - Final

    Inspected by Troy Crews